Solar panels and EV chargers in Blythe

Blythe's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Blythe Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Blythe's code says

Blythe code What Blythe's code adds
EV charger permit
  • Approved administratively, with all needed permits issued, once the application meets the checklist, applicable laws and health and safety standards.
    Applies: Electric vehicle charging station permit applications that meet the city's adopted checklist.
    § 15.64.050 · code text
    Upon confirmation by the building official that the permit application and supporting documents meet the requirements of the city's adopted checklist, and is consistent with all applicable laws and health and safety standards, the building official shall, consistent with California Government Code Section 65850.7, administratively approve the application and issue all necessary permits.
  • Electronic submittal and electronic signatures are accepted.
    Applies: Electric vehicle charging station permit applications and supporting documents.
    § 15.64.050 · code text
    the building official shall allow for electronic submittal of permit applications and associated supporting documentation. In accepting such permit applications, the building official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.
Solar permit process
  • Expedited, nondiscretionary review; the permit is issued as soon as possible after a complete submittal.
    Applies: Small residential rooftop solar systems that meet the approved checklist and standard plan.
    § 15.62.070 · code text
    For an application for a small residential rooftop solar energy system that meets the requirements of the approved checklist and standard plan, the building department shall issue a building permit or other non-discretionary permit as soon as possible following a complete submittal.
  • Only one inspection; it is scheduled within 2 business days with a 2-hour inspection window.
    Applies: Small residential rooftop solar systems eligible for expedited review.
    § 15.62.070 · code text
    Only one inspection shall be required and performed by the building department for small residential rooftop solar energy systems eligible for expedited review.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Blythe?

Blythe's code: Expedited, nondiscretionary review; the permit is issued as soon as possible after a complete submittal. (Small residential rooftop solar systems that meet the approved checklist and standard plan.) (§ 15.62.070); Approved administratively, with all needed permits issued, once the application meets the checklist, applicable laws and health and safety standards. (Electric vehicle charging station permit applications that meet the city's adopted checklist.) (§ 15.64.050).

General information, not legal advice.