El Dorado County CPO zoning: height, setbacks and lot size

In El Dorado County's CPO zone, buildings can be up to 50 ft tall, the front setback is 10 ft and the minimum lot size is 6,000 sq ft (El Dorado County code, read October 2026).

Key points

  • Maximum building height: 50 ft
  • Minimum front setback: 10 ft
  • Minimum side setback: 5 ft (Unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code)
  • Minimum rear setback: 5 ft (Unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code)
  • Minimum lot size: 6,000 sq ft
  • Maximum floor area ratio (FAR): 0.85

CPO is a zoning district in El Dorado County. Every value below was read from the El Dorado County Municipal Code and links to its section (read October 2026). State laws such as the ADU and SB 9 rules can allow more on a residential lot. General information, not legal advice — read the code text and check with the city before you build.

Development standards in CPO

The general rule for a typical lot in this zone. Zoning tables often attach notes, such as rules for corner lots, lots next to a residential zone, or new subdivisions only. Open “code text” under a value to see the table cell or sentence it was read from.

Maximum building height
50 ft
§ 130.22.030 · code text
Table row “Maximum Building Height (in feet)”, column “CPO”: 50
Minimum front setback
10 ft
See note 3 below the table in the code.
§ 130.22.030 · code text
Table row “Setbacks (in feet) Front and Second- ary Front 3”, column “CPO”: 10
Note 3: Subject to Landscaping requirements in the site planning and design manual.
Minimum side setback
5 ft
Applies: Unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code
See note 4 below the table in the code.
§ 130.22.030 · code text
Table row “Sides and Rear 4”, column “CPO”: 0 or 5
Note 4: Zero lot line with fireproof wall and no openings, meeting building and fire code requirements, otherwise the 5 foot setback applies.
Minimum rear setback
5 ft
Applies: Unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code
See note 4 below the table in the code.
§ 130.22.030 · code text
Table row “Sides and Rear 4”, column “CPO”: 0 or 5
Note 4: Zero lot line with fireproof wall and no openings, meeting building and fire code requirements, otherwise the 5 foot setback applies.
Minimum lot size
6,000 sq ft
§ 130.22.030 · code text
Table row “Minimum Lot Size 1 (in square feet)”, column “CPO”: 6,000
Maximum floor area ratio (FAR)
0.85
See note 6 below the table in the code.
§ 130.22.030 · code text
Table row “Floor Area Ratio 6”, column “CPO”: .85
Note 6: Ratio of allowable floor area to lot area.

Uses in CPO

Uses the code's use tables allow in CPO, or allow with a permit. Each links to its page with the code section.

When a different number applies

The code sets other values for particular lots, buildings or locations in CPO:

  • Minimum side setback: 10 or 30 ft — Abutting R, R1A, R2A, R3A, and RE zoned land; the table does not say when 10 or 30 applies § 130.22.030
  • Minimum rear setback: 10 or 30 ft — Abutting R, R1A, R2A, R3A, and RE zoned land; the table does not say when 10 or 30 applies § 130.22.030

Not on this page

We did not find a general stories, lot coverage, density limit for CPO in the zoning tables we read. The code may still set one elsewhere — check the El Dorado County Municipal Code.

Other El Dorado County zoning districts

Who this affects

HomeownersArchitects and designersDevelopersReal estate agents

Frequently asked questions

What is the maximum building height in El Dorado County's CPO zone?

50 ft — El Dorado County Municipal Code § 130.22.030.

What is the minimum front setback in El Dorado County's CPO zone?

10 ft — El Dorado County Municipal Code § 130.22.030.

What is the minimum side setback in El Dorado County's CPO zone?

5 ft (unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code) — El Dorado County Municipal Code § 130.22.030.

What is the minimum rear setback in El Dorado County's CPO zone?

5 ft (unless a zero lot line is used: 0 ft with a fireproof wall and no openings that meets building and fire code) — El Dorado County Municipal Code § 130.22.030.

What is the minimum lot size in El Dorado County's CPO zone?

6,000 sq ft — El Dorado County Municipal Code § 130.22.030.

General information, not legal advice.

Ask about an El Dorado County property in CPO

Ask GoCodebook what you can build at a specific address and get an answer that cites the section.

Ask your question

More on El Dorado County