Skip to content

Guadalupe · Building on your lot

Solar panels and EV chargers in Guadalupe

Guadalupe's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Guadalupe Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Guadalupe's code says

Guadalupe code What Guadalupe's code adds
EV charger permit
  • The Building Official approves applications meeting the city checklist, laws and safety standards, issuing all permits; electronic submittal allowed.
    Applies: Electric vehicle charging stations.
    § 15.16.040 · code text
    the Building Official or delegee shall allow for electronic submittal of permit applications covered by the ordinance codified in this chapter and associated supporting documentations.
Solar permit process
  • Administrative, nondiscretionary building permit when a complete application meets the checklist and standard plan; only one inspection.
    Applies: Small residential rooftop solar systems.
    § 15.14.060 · code text
    The Building Division shall issue a nondiscretionary building permit the same day for over-the-counter applications, if possible,
Review time
  • Same day if possible, otherwise within 24 hours.
    Applies: Small residential rooftop solar; complete over-the-counter application meeting the approved checklist and standard plan, if possible.
    § 15.14.060 · code text
    The Building Division shall issue a nondiscretionary building permit the same day for over-the-counter applications, if possible,
  • Within 24 hours.
    Applies: Small residential rooftop solar with a complete over-the-counter application, when same-day issue is not possible.
    § 15.14.060 · code text
    or otherwise, within 24 hours, or within 3 business days for electronic applications, of receipt of a complete application
  • Within 3 business days.
    Applies: Small residential rooftop solar with a complete electronic application.
    § 15.14.060 · code text
    or within 3 business days for electronic applications, of receipt of a complete application

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Guadalupe?

Guadalupe's code: Administrative, nondiscretionary building permit when a complete application meets the checklist and standard plan; only one inspection. (Small residential rooftop solar systems.) (§ 15.14.060); The Building Official approves applications meeting the city checklist, laws and safety standards, issuing all permits; electronic submittal allowed. (Electric vehicle charging stations.) (§ 15.16.040).

General information, not legal advice.

Ask about a specific Guadalupe property

Ask GoCodebook how Guadalupe's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Guadalupe