| City help |
-
The city may replace the sidewalk for the owner, but the owner pays all costs unless a council program helps. Applies: The owner asks the city to do the work, and the city agrees at its sole discretion.
§ 12.20.030 · code textIf the city, in its sole discretion, agrees to such a request, the city may perform the work with city forces or may contract with a vendor of the city's choosing to perform the work.
|
| If the owner does not repair |
-
The city may repair it for the owner, who pays the city's costs, including inspection, admin, collection and lien handling. Applies: The owner does not maintain and repair the sidewalk as the chapter requires.
§ 12.20.030 · code textIn the event a property owner fails to maintain and repair a sidewalk in accordance with this chapter, the owner will be responsible for costs incurred by the city in undertaking maintenance and repair work on the owner's behalf, including, without limitation, any charge for the city's costs of inspection and administration whenever the city awards a contract for such work, the costs of collecting the city's expenses for the maintenance and repair work, and the handling of any lien placed on the property due to the failure of the property owner to promptly pay the city's costs.
-
The city may record a lien on the property or add the amount owed to the property tax bill. Applies: Costs confirmed by the city council after the required hearing.
§ 12.20.090 · code textSuch remedies include the recording of a lien against an owner's property or adding the amount owed to the city to the tax roll for the subject property.
|
| Liability for injuries |
|
| Deadline to repair |
-
The work must be finished within 30 calendar days of the city's notice. Applies: A defective sidewalk section will be replaced to remove a hazard.
§ 12.20.030 · code textIf a section of defective sidewalk will be replaced to eliminate a hazard, the process to remove the defective sidewalk and install new sidewalk shall be completed within 30 calendar days of the date of the notice given by the city pursuant to Section 12.20.050 below.
-
The owner must install the new sidewalk within 7 calendar days after the city removes the old one. Applies: The city demolishes and removes the defective sidewalk.
§ 12.20.030 · code textthe landowner must complete the installation of the replacement sidewalk within seven calendar days of the completion of the city's demolition and removal the defective sidewalk.
|
| Who must repair it |
-
The owner of the adjacent or fronting lot must maintain and repair the sidewalk at their sole cost.
§ 12.20.030 · code textExcept as otherwise provided in this chapter, an owner of a lot or portion of a lot adjacent to or fronting any portion of a sidewalk area or on which a sidewalk area is located shall maintain and repair the sidewalk so that it remains a safe and non-dangerous condition at his/her/its sole cost and expense.
-
The city pays to grind, or if that fails, to remove the defect; the owner pays to replace removed sidewalk. Applies: The defect was not caused by the owner or their workers, agents, guests or contractors; tree root damage is not the owner's fault.
§ 12.20.030 · code textThe city will, at its own cost, grind the defective sidewalk to eliminate the hazard if grinding is feasible. If grinding will not eliminate the hazard, the city shall, at the city's expense, demolish and remove the defective portion of sidewalk, and the owner will, at the owner's sole cost, replace the portion of sidewalk removed by the city.
-
The owner alone is responsible for all repair work to fix the hazard. Applies: The city reasonably finds the defect was caused on purpose or by negligence of the owner or their workers, agents, guests or contractors.
§ 12.20.030 · code textIf the city reasonably determines that the defective sidewalk was caused by the intentional misconduct or negligence of the owner or the owner's employee, agent, invitee, or contractor, the owner shall be solely responsible for all repair work required to address the hazard.
|