Solar panels and EV chargers in Lemon Grove

Lemon Grove's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Lemon Grove Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Lemon Grove's code says

Lemon Grove code What Lemon Grove's code adds
Solar permit process
  • Administrative, nondiscretionary review; all permits are issued when the complete application meets the checklist; only 1 inspection.
    Applies: Applies to small residential rooftop solar systems.
    § 15.33.060 · code text
    The planning and building department shall implement an administrative, nondiscretionary review process to expedite approval of small residential rooftop solar energy systems.
  • Apply in person, by mail, or electronically (email, fax or online), with the required processing and inspection fees.
    Applies: Applies to small residential rooftop solar permit applicants.
    § 15.33.050 · code text
    Electronic submittal of the required permit application and documents by e-mail, fax, or the Internet shall be made available to all small residential rooftop solar energy system permit applicants.
Review time
  • Deemed approved if not denied in writing within 45 days of receipt.
    Applies: Small residential rooftop solar, unless the delay comes from a reasonable request for more information.
    § 15.33.060 · code text
    If an application is not denied in writing within forty-five days from the date of receipt of the application, the application shall be deemed approved, unless that delay is the result of a reasonable request for additional information.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Lemon Grove?

Lemon Grove's code: Administrative, nondiscretionary review; all permits are issued when the complete application meets the checklist; only 1 inspection. (Applies to small residential rooftop solar systems.) (§ 15.33.060); Apply in person, by mail, or electronically (email, fax or online), with the required processing and inspection fees. (Applies to small residential rooftop solar permit applicants.) (§ 15.33.050).

General information, not legal advice.