Grading and erosion control in Menifee

Menifee's own rules on grading and erosion control, with the code text for every value.

Each rule below links to the section of the Menifee Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Menifee's code says

Menifee code What Menifee's code adds
Erosion control plan
  • Work needing a grading permit or grading plan needs an approved erosion control plan.
    Applies: Unless the City Engineer/Public Works Director waives it; plan contents may be waived or varied for single home lots.
    § 7.90.060 · code text
    Unless waived by the City Engineer/Public Works Director, all work requiring a grading permit or a grading plan shall be required to have an approved erosion control plan.
  • A project needs an erosion control plan if erosion or sediment could harm neighboring properties.
    Applies: As the City Engineer/Public Works Director decides.
    § 7.90.060 · code text
    An erosion control plan is required for a project if the City Engineer/Public Works Director determines that erosion or sediment discharge from the project could adversely affect adjacent properties.
When a grading permit is needed
  • You need a grading permit for more than 50 cubic yards.
    Applies: Stockpiling, depositing, placing or removing earth on a property.
    § 7.90.030 · code text
    No person shall stockpile, deposit, or allow the placement or removal of earth material on or from any real property in excess of 50 cubic yards without first obtaining a grading permit.
Grading without a permit
  • Digs up to 50 cubic yards/site: under 2 feet deep, or no cut over 5 feet and steeper than 2:1.
    § 7.90.030 · code text
    An excavation not exceeding 50 cubic yards on a single site that is less than two feet in vertical depth or that does not create a cut slope greater than five feet in vertical height and steeper than a two to one (2:1) horizontal to vertical ratio.
  • Fill up to 50 cubic yards/site, under 1 foot deep, on ground flatter than 5:1, not blocking a drainage course.
    § 7.90.030 · code text
    A fill not exceeding 50 cubic yards on a single site that is less than one foot in depth, that does not obstruct a drainage course and that is placed on natural grade with a slope flatter than a five to one (5:1) horizontal to vertical ratio.
  • Exempt: digging for basements and footings of a building, mobile home, retaining wall, pool or other permitted structure.
    Applies: Not fill made from the dug soil, nor a dig left over 5 feet high unsupported or with vertical banks over 2 feet.
    § 7.90.030 · code text
    An excavation below finish grade for basements and footings of a building, mobile home, retaining wall, swimming pool, or other structure authorized by a valid building permit or construction permit.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What are the grading rules in Menifee?

Menifee's code: You need a grading permit for more than 50 cubic yards. (Stockpiling, depositing, placing or removing earth on a property.) (§ 7.90.030); Work needing a grading permit or grading plan needs an approved erosion control plan. (Unless the City Engineer/Public Works Director waives it; plan contents may be waived or varied for single home lots.) (§ 7.90.060).

General information, not legal advice.

Ask about a specific Menifee property

Ask GoCodebook how Menifee's grading and erosion control rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Menifee