Solar panels and EV chargers in Morgan Hill

Morgan Hill's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Morgan Hill Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Morgan Hill's code says

Morgan Hill code What Morgan Hill's code adds
EV-ready new homes
  • 1 garage space must be Level 2 EV Ready; a second space, if provided, must be Level 1 EV Ready.
    Applies: New homes with private dedicated garages.
    § 15.62.060 · code text
    One parking space provided in the garages shall be a Level 2 EV Ready space.
  • 40% of spaces: EVCS with Level 2 EV Ready; 60%: at least a Level 1 EV Ready space.
    Applies: New multifamily residential buildings with shared parking.
    § 15.62.060 · code text
    Forty percent of parking spaces shall be EVCS with Level 2 EV Ready.
EV charger permit
  • Approved administratively through a building permit or similar nondiscretionary permit.
    Applies: EV charging station applications that meet the city checklist and local, state and federal health and safety requirements.
    § 15.37.060 · code text
    The building department shall administratively approve an application to install electric vehicle charging stations through issuance of a building permit or similar nondiscretionary permit.
Solar permit process
  • Administrative, nondiscretionary review; permit issued when a complete application meets the standard plan and checklist; 1 inspection.
    Applies: Small residential rooftop solar systems; the inspection is scheduled within 2 business days of a request.
    § 15.36.060 · code text
    The building department shall issue a building permit or other nondiscretionary permit the same day for over-the-counter applications or within one to three business days for electronic applications upon receipt of a complete application meeting the requirements of the approved standard plan and checklist.
Review time
  • Same day for over-the-counter applications; 1 to 3 business days for electronic applications.
    Applies: Complete applications for small residential rooftop solar energy systems.
    § 15.36.060 · code text
    The building department shall issue a building permit or other nondiscretionary permit the same day for over-the-counter applications or within one to three business days for electronic applications upon receipt of a complete application meeting the requirements of the approved standard plan and checklist.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Morgan Hill?

Morgan Hill's code: Administrative, nondiscretionary review; permit issued when a complete application meets the standard plan and checklist; 1 inspection. (Small residential rooftop solar systems; the inspection is scheduled within 2 business days of a request.) (§ 15.36.060); Approved administratively through a building permit or similar nondiscretionary permit. (EV charging station applications that meet the city checklist and local, state and federal health and safety requirements.) (§ 15.37.060).

General information, not legal advice.