Paso Robles's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Paso Robles Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Paso Robles's code says

Paso Robles code What Paso Robles's code adds
EV charger permit
  • The building official approves applications meeting the city checklist, laws and safety standards, and issues all needed permits.
    Applies: Electric vehicle charging stations; the station may not be energized or used until the city approves it.
    § 17.25.040 · code text
    A permit application that satisfies the information requirements in the city's adopted checklist shall be deemed complete and be promptly processed.
  • Permit applications may be submitted electronically; electronic signatures are accepted.
    Applies: Electric vehicle charging station permit applications.
    § 17.25.040 · code text
    Consistent with Government Code Section 65850.7, the building official shall allow for electronic submittal of permit applications covered by this chapter and associated supporting documentation.
Solar permit process
  • City staff issue a nondiscretionary permit within a reasonable time after a complete application meets the checklist and standard plan.
    Applies: Small residential rooftop solar systems, unless the director requires a use permit.
    § 17.20.060 · code text
    Unless the director determines a use permit is warranted, city staff shall issue a building permit or other nondiscretionary permit within a reasonable period of time after receipt of a complete application that meets the requirements of the approved checklist, standard plan and this article.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Paso Robles?

Paso Robles's code: City staff issue a nondiscretionary permit within a reasonable time after a complete application meets the checklist and standard plan. (Small residential rooftop solar systems, unless the director requires a use permit.) (§ 17.20.060); The building official approves applications meeting the city checklist, laws and safety standards, and issues all needed permits. (Electric vehicle charging stations; the station may not be energized or used until the city approves it.) (§ 17.25.040).

General information, not legal advice.

Ask about a specific Paso Robles property

Ask GoCodebook how Paso Robles's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Paso Robles