What Rancho Cordova's code says

Rancho Cordova code What Rancho Cordova's code adds
Solar permit process
  • Administrative, nondiscretionary review. A permit is issued when the application meets the approved checklist and standard plan.
    Applies: Applies to small home rooftop solar energy systems eligible for expedited review.
    § 16.07.060 · code text
    The building department shall issue a building permit, the issuance of which is nondiscretionary, within three business days upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.
  • 1 inspection. Requested inspections are scheduled within 1 to 3 business days.
    Applies: Small home rooftop solar eligible for expedited review. The local fire district may require a separate inspection.
    § 16.07.060 · code text
    Only one inspection shall be required and performed by the building department for small residential rooftop solar energy systems eligible for expedited review.
Review time
  • The permit is issued within 3 business days.
    Applies: Small home rooftop solar, with a complete application that meets the approved checklist and standard plan.
    § 16.07.060 · code text
    The building department shall issue a building permit, the issuance of which is nondiscretionary, within three business days upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Rancho Cordova?

Rancho Cordova's code: Administrative, nondiscretionary review. A permit is issued when the application meets the approved checklist and standard plan. (Applies to small home rooftop solar energy systems eligible for expedited review.) (§ 16.07.060); 1 inspection. Requested inspections are scheduled within 1 to 3 business days. (Small home rooftop solar eligible for expedited review. The local fire district may require a separate inspection.) (§ 16.07.060).

General information, not legal advice.

Ask about a specific Rancho Cordova property

Ask GoCodebook how Rancho Cordova's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Rancho Cordova