Solar panels and EV chargers in Richmond
Complete small rooftop solar applications meeting the checklist get permits in 3 business days, with inspections within 2 business days of request.
Key points
- Rooftop solar: Complete small rooftop solar applications meeting the checklist get permits in 3 business days, with inspections within 2 business days of request.
Each rule below links to the section of the Richmond Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.
What Richmond's code says
| EV charger permit |
|
|---|---|
| Solar permit process |
|
| Review time |
|
Who this affects
Frequently asked questions
Do I need a permit for solar panels or an EV charger in Richmond?
Complete small rooftop solar applications meeting the checklist get permits in 3 business days, with inspections within 2 business days of request.
General information, not legal advice.
Ask about a specific Richmond property
Ask GoCodebook how Richmond's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.
Ask your questionMore on building on your lot in Richmond
All building on your lot rules in Richmond
Fences and walls in Richmond
Sheds, garages and other accessory structures in Richmond
Running a business from home in Richmond
Swimming pools in Richmond
Building on a hillside in Richmond
Noise and construction hours in Richmond
Affordable units in new housing (inclusionary) in Richmond
Home alarm permits and false alarms in Richmond
Trash and recycling carts in Richmond
Historic homes in Richmond
Richmond Municipal Code — full text