San Joaquin County · Building on your lot

Solar panels and EV chargers in San Joaquin County

San Joaquin County's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the San Joaquin County Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What San Joaquin County's code says

San Joaquin County code What San Joaquin County's code adds
EV charger permit
  • Expedited permits: submit an application and checklist on Department forms with any required fee.
    § 8-3004 · code text
    The applicant shall submit a permit application and checklist on forms provided by the Department along with any required fee. The Department shall review the application and checklist to determine whether it is complete and eligible for expedited permitting.
  • Electronic filing and electronic signatures are accepted.
    § 8-3004 · code text
    The Department shall allow for electronic submittal of permit applications covered by this Ordinance. In accepting such permit applications, the Department shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by the applicant.
  • No discretionary use permit is required.
    § 8-3005 · code text
    The Department shall confirm information provided in the application and checklist is consistent with all applicable laws and health and safety standards and shall not require any discretionary use permit.
Solar height and setbacks
  • Up to 5 feet above the zone's height limit.
    Applies: Small residential rooftop solar systems on single-unit lots.
    § 9-400.060 · code text
    A small residential rooftop solar energy system may extend up to five feet above the height limit in the zone in which it is located.
  • Up to 7 feet above the zone's height limit.
    Applies: Solar water or pool heating systems on single-unit lots.
    § 9-400.060 · code text
    Solar water or swimming pool heating systems may extend up to seven feet above the height limit in the zone in which it is located.
  • Up to 5 feet above the roof surface, even if this exceeds the zone's height limit.
    Applies: Small residential rooftop solar systems on all other lots.
    § 9-400.060 · code text
    A small residential rooftop solar energy system may extend up to five feet above the roof surface on which they are installed, even if this exceeds the maximum height limit in the zone in which it is located.
  • Up to 7 feet above the roof surface, even if this exceeds the zone's height limit.
    Applies: Solar water or pool heating systems on all other lots.
    § 9-400.060 · code text
    Solar water or swimming pool heating systems may extend up to seven feet above the roof surface on which they are installed even if this exceeds the maximum height limit in the zone in which it is located.
  • Equipment other than collector panels may be in side or rear setbacks, at least 3 feet from any lot line.
    Applies: Small residential rooftop solar energy systems.
    § 9-400.060 · code text
    Excluding solar collector panels, solar energy system equipment may be installed within a required side and rear setback, but must not be closer than three feet to any lot line.
Solar permit process
  • Expedited administrative review; only a Zoning Compliance Review is needed, with checklist-based processing.
    Applies: Approved administratively unless specific adverse impacts are found.
    § 9-400.060 · code text
    After receipt of a complete application, only a Zoning Compliance Review is required for issuance of a building permit, and the building permitting process shall be streamlined with use of checklists to determine compliance with standards and eligibility for expedited review.
  • Electronic filing and electronic signatures are allowed.
    Applies: Where available resources allow it.
    § 8-2002 · code text
    As allowed by available resources, the Department shall allow for electronic submittal of a permit application and associated documentation and shall allow electronic signature in lieu of a wet signature.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in San Joaquin County?

San Joaquin County's code: Expedited administrative review; only a Zoning Compliance Review is needed, with checklist-based processing. (Approved administratively unless specific adverse impacts are found.) (§ 9-400.060); Expedited permits: submit an application and checklist on Department forms with any required fee. (§ 8-3004).

General information, not legal advice.

Ask about a specific San Joaquin County property

Ask GoCodebook how San Joaquin County's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in San Joaquin County