What Saratoga's code says

Saratoga code What Saratoga's code adds
Grading without a permit
  • Excavation that is less than two feet deep, or that does not create a cut slope that is both greater than five feet in height and steeper than one vertical in one and one-half horizontal (66.7 percent slope); fill less than one foot deep on natural terrain flatter than one vertical in five horizontal (twenty percent slope), or less than three feet deep, not intended to support structures, that does not exceed fifty cubic yards on any one lot and does not obstruct a drainage course; basement and footing excavation under a valid building permit (not fill made from it, and not an excavation with an unsupported height greater than five feet)
    Applies: A grading permit is not required for this work
    § 16-17.030 · code text
    does not create a cut slope greater than five feet (one thousand five hundred twenty-four mm) in height and steeper than one unit vertical in one and one-half units horizontal (66.7 percent slope).
  • Excavation under 2 feet deep, or a cut slope up to 5 feet high or no steeper than 66.7%.
    Applies: Fill under 1 foot on slopes under 20%, or under 3 feet, up to 50 cubic yards per lot, not supporting structures or blocking drainage.
    § 16-17.030 · code text
    An excavation that (1) is less than two feet (six hundred ten mm) in depth or (2) does not create a cut slope greater than five feet (one thousand five hundred twenty-four mm) in height and steeper than one unit vertical in one and one-half units horizontal (66.7 percent slope).
  • Digging below finished grade for basements and footings of a building, wall or other structure with a valid building permit.
    Applies: Does not exempt fill made from the excavated material, or excavation with unsupported height over 5 feet after completion.
    § 16-17.030 · code text
    An excavation below finished grade for basements and footings of a building, retaining wall or other structure authorized by a valid building permit.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

What are the grading rules in Saratoga?

Saratoga's code: Excavation that is less than two feet deep, or that does not create a cut slope that is both greater than five feet in height and steeper than one vertical in one and one-half horizontal (66.7 percent slope); fill less than one foot deep on natural terrain flatter than one vertical in five horizontal (twenty percent slope), or less than three feet deep, not intended to support structures, that does not exceed fifty cubic yards on any one lot and does not obstruct a drainage course; basement and footing excavation under a valid building permit (not fill made from it, and not an excavation with an unsupported height greater than five feet) (A grading permit is not required for this work) (§ 16-17.030); Excavation under 2 feet deep, or a cut slope up to 5 feet high or no steeper than 66.7%. (Fill under 1 foot on slopes under 20%, or under 3 feet, up to 50 cubic yards per lot, not supporting structures or blocking drainage.) (§ 16-17.030).

General information, not legal advice.

Ask about a specific Saratoga property

Ask GoCodebook how Saratoga's grading and erosion control rules apply to your situation and get an answer that cites the section.

Ask your question

More on building on your lot in Saratoga