Solar panels and EV chargers in Sausalito

Sausalito's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Sausalito Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Sausalito's code says

Sausalito code What Sausalito's code adds
EV charger permit
  • Expedited administrative approval through a building permit or similar nondiscretionary permit.
    Applies: Applies to a completed application that meets all requirements of the City's checklist.
    § 8.56.040 · code text
    The City shall administratively approve an application to install electric vehicle charging station through the issuance of a building permit or similar nondiscretionary permit.
Review time
  • The same day.
    Applies: Complete over-the-counter applications that meet the approved checklist and standard plan.
    § 10.70.060 · code text
    Upon receipt of a complete application that satisfies the requirements of the approved checklist and standard plan, the Building Department shall issue a building permit or other nondiscretionary permit the same day for over-the-counter applications, and within one to three business days for electronic applications.
  • Within 1 to 3 business days.
    Applies: Complete electronic applications that meet the approved checklist and standard plan.
    § 10.70.060 · code text
    Upon receipt of a complete application that satisfies the requirements of the approved checklist and standard plan, the Building Department shall issue a building permit or other nondiscretionary permit the same day for over-the-counter applications, and within one to three business days for electronic applications.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Sausalito?

Sausalito's code: The same day. (Complete over-the-counter applications that meet the approved checklist and standard plan.) (§ 10.70.060); Expedited administrative approval through a building permit or similar nondiscretionary permit. (Applies to a completed application that meets all requirements of the City's checklist.) (§ 8.56.040).

General information, not legal advice.

Ask about a specific Sausalito property

Ask GoCodebook how Sausalito's solar panels and EV chargers rules apply to your situation and get an answer that cites the section.