Solar panels and EV chargers in Seal Beach

Seal Beach's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Seal Beach Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Seal Beach's code says

Seal Beach code What Seal Beach's code adds
EV charger permit
  • Expedited nondiscretionary building permit; apply in person, by mail or electronically; issued when the application meets the checklist.
    Applies: Installing an EV charging station anywhere in the city.
    § 9.60.090.040 · code text
    Anyone seeking to install an electric vehicle charging station at any site within the city may apply to the building official for an expedited nondiscretionary building permit.
  • If the application is incomplete, a written correction notice is available within 10 working days.
    Applies: Expedited building permit applications for EV charging stations.
    § 9.60.090.040 · code text
    If an application is deemed incomplete, a written plan check correction notice will be available to the applicant within 10 working days
Solar permit process
  • Administrative approval and all required permits once the application is confirmed complete and meets the checklist and standard plans.
    Applies: Small residential rooftop solar systems eligible for expedited review.
    § 9.60.050.060 · code text
    the building official shall administratively approve the application and issue all required permits or authorizations.
  • Only 1 inspection.
    Applies: Small residential rooftop solar systems eligible for expedited review.
    § 9.60.050.060 · code text
    For a small residential rooftop solar energy system eligible for expedited review, only one inspection shall be required

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Seal Beach?

Seal Beach's code: Administrative approval and all required permits once the application is confirmed complete and meets the checklist and standard plans. (Small residential rooftop solar systems eligible for expedited review.) (§ 9.60.050.060); Expedited nondiscretionary building permit; apply in person, by mail or electronically; issued when the application meets the checklist. (Installing an EV charging station anywhere in the city.) (§ 9.60.090.040).

General information, not legal advice.