§ 21168.6.8. SPORTS AND ENTERTAINMENT PROJECT
CEQA Statute and Guidelines (2025 consolidated text) · 2026 edition · updated 2026-07-29 · California
(a) For the purposes of this section, the following definitions apply:
(1) “Applicant” means a private or public entity or its affiliates that proposes to implement and operate all or any portion of the project and its successors, heirs, and assignees.
(2) “Arena” means an 18,000 to 20,000 seat arena built as part of the project for National Basketball Association (NBA) basketball games and other spectator events.
(3) “Project” means a project located within the project area consisting of the arena plus practice and athletic training facility, and related parking and access, infrastructure construction or relocation, and landscaping, up to approximately 75,000 square feet of associated office space, up to approximately 30,000 square feet of sports medicine clinic space, up to approximately 70,000 square feet of ancillary retail, restaurant, community space, and similar uses, and a hotel, provided that the project meets all of the following:
(A) Receives Leadership in Energy and Environmental Design (LEED) gold certification for new construction within one year of the completion of the first NBA season.
(B) (i) Requires a transportation demand management program that, upon full implementation, will achieve and maintain a 15-percent reduction in the number
138
Association of Environmental Professionals 2025
CEQA Statute
of vehicle trips, collectively, by attendees, employees, visitors, and customers as compared to operations absent the transportation demand management program.
- (ii) To accelerate and maximize vehicle trip reduction, each measure in the transportation demand management program shall be implemented as soon as feasible, so that no less than a 7.5-percent reduction in vehicle trips is achieved and maintained by the end of the first NBA season during which an NBA team has played at the arena.
- (iii) A 15-percent reduction in vehicle trips shall be achieved and maintained as soon as feasible, but not later than January 1, 2030. The applicant shall verify achievement to the lead agency and the Office of Planning and Research.
- (iv) If the applicant fails to verify achievement of the reduction required by clause (iii) , the lead agency shall impose additional feasible measures to reduce vehicle trips by 17 percent, or, if there is a rail transit line with a stop within one-quarter mile of the arena, 20 percent, by January 1, 2035.
(C) Is located on an infill site.
(D) Is consistent with the general use designation, density, building intensity, and applicable policies specified for the project area in either a sustainable communities strategy or an alternative planning strategy for which the State Air Resources Board, pursuant to subparagraph (H) of paragraph (2) of subdivision (b) of Section 65080 of the Government Code, has accepted a metropolitan planning organization’s determination that the sustainable communities strategy or the alternative planning strategy would, if implemented, achieve the greenhouse gas emission reduction targets.
alternative planning strategy for which the State Air Resources Board, pursuant to subparagraph (H) of paragraph (2) of subdivision (b) of Section 65080 of the Government Code, has accepted a metropolitan planning organization’s determination that the sustainable communities strategy or the alternative planning strategy would, if implemented, achieve the greenhouse gas emission reduction targets.
(4) “Project approval” means any action, activity, ordinance, resolution, agreement, approval, determination, finding, or decision taken, adopted, or approved by the lead agency required to allow the applicant to commence the construction of the project, as determined by the lead agency.
(5) “Project area” means real property in the City of Inglewood consisting of approximately 35 acres, including without limitation areas generally described as follows:
(A) Assessor identification numbers 4032-001-005, 4032-001-006, 4032-001-033, 4032001-035, 4032-001-039, 4032-001-048, 4032-001-049, 4032-001-900 to 4032-001913, inclusive, 4032-002-913 to 4032-002-917, inclusive, 4032-003-912, 4032-003914, 4032-003-915, 4032-004-913, 4032-004-914, 4032-007-035, 4032-007-900 to 4032-007-905, inclusive, 4032-008-001, 4032-008-002, 4032-008-006, 4032-008034, 4032-008-035, 4032-008-900 to 4032-008-905, inclusive, 4032-008-907, 4032008-908, 4034-004-026, 4034-004-900 to 4034-004-913, inclusive, and 4034-005900 to 4034-005-912, inclusive.
(B) West 101st Street from its intersection with South Prairie Avenue westerly to a line approximately 488 feet west of the western boundary of South Prairie Avenue, and West 102nd Street from its intersection with South Prairie Avenue easterly to a line approximately 883 feet east of the eastern boundary of South Prairie Avenue.
(C) Adjacent areas or air space to be used for access.
(6) “Transportation demand management program” means a specific program of strategies, incentives, and tools to be implemented, with specific annual status reporting obligations in accordance with paragraph (5) of subdivision (b) , to reduce vehicle trips by providing opportunities for event attendees and employees to choose sustainable travel options such
139
Association of Environmental Professionals 2025
CEQA Statute
as transit, bicycle riding, or walking. A specific program of strategies, incentives, and tools includes, but is not limited to, the following:
- (A) Provision of shuttles, charter buses, or similar services from a major transit stop to serve arena events.
- (B) Provision of onsite electric vehicle charging stations in excess of applicable requirements.
- (C) Provision of dedicated parking for car-share or zero-emission vehicles, or both types of vehicle, in excess of applicable requirements.
- (D) Provision of bicycle parking in excess of applicable requirements.
- (E) Inclusion of a transit facility with area dedicated to shuttle bus staging, ride share, bicycle parking, and other modalities intended to reduce the use of single occupant vehicles.
(b) The Governor may certify the project for streamlining pursuant to this section if all the following conditions are met:
(1) The project will result in a minimum investment of one hundred million dollars ($100,000,000) in California upon completion of construction.
(2) (A) (i) The project creates high-wage, highly skilled jobs that pay prevailing wages and living wages, employs a skilled and trained workforce, as defined in subdivision (d) of Section 2601 of the Public Contract Code, provides construction jobs and permanent jobs for Californians, and helps reduce unemployment. For purposes of this subdivision, “jobs that pay prevailing wages” means that all construction workers employed in the execution of the project will receive at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code. If the project is certified for streamlining, the project applicant shall include this requirement in all contracts for the performance of the work.
- (ii) Clause (i) does not apply to a contractor or subcontractor performing the work on the project that is subject to a project labor agreement requiring the payment of prevailing wages to all construction workers employed in the execution of the project and providing for enforcement of that obligation through an arbitration procedure. For purposes of this clause, “project labor agreement” has the same meaning as set forth in paragraph (1) of subdivision of Section 2500 of the Public Contract Code.(B) (i) If the project is certified pursuant to this subdivision, contractors and subcontractors shall pay to all construction workers employed in the execution of the project at least the general prevailing rate of per diem wages.
- (ii) Except as provided in clause (iii) , the obligation of the contractors and subcontractors to pay prevailing wages pursuant to subparagraph (A) may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code, within 18 months after the completion of the project, or by an underpaid worker through an administrative complaint or civil action. If a civil wage and penalty assessment is issued, the contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
140
Association of Environmental Professionals 2025
CEQA Statute
(iii) Clause (ii) does not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this subparagraph, “project labor agreement” has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(3) The project does not result in any net additional emission of greenhouse gases, including greenhouse gas emissions from employee transportation, as determined by the State Air Resources Board pursuant to Division 25.5 (commencing with Section 38500) of the Health and Safety Code. The State Air Resources Board is encouraged to make its determination no later than 120 calendar days after receiving an application for review of the methodology and calculations of the project’s greenhouse gas emissions.
(4) The project applicant demonstrates compliance with the requirements of Chapters 12.8 (commencing with Section 42649) and 12.9 (commencing with Section 42649.8) of Part 3 of Division 30, as applicable.
(5) The project applicant has entered into a binding and enforceable agreement that all mitigation measures required pursuant to this division and any other environmental measures required by this section to certify the project under this section shall be conditions of approval of the project, and those conditions will be fully enforceable by the lead agency or another agency designated by the lead agency. In the case of environmental mitigation measures and any other environmental measures required by this section, the applicant agrees, as an ongoing obligation, that those measures will be monitored and enforced by the lead agency for the life of the obligation. The project applicant shall submit to the lead agency an annual status report on the implementation of the environmental mitigation measures and any other environmental measures required by this section.
(6) The project applicant agrees to pay any additional costs incurred by the courts in hearing and deciding any case subject to this section, including payment of the costs for the appointment of a special master if deemed appropriate by the court, in a form and manner specified by the Judicial Council, as provided in the Rules of Court adopted by the Judicial Council.
(7) The project applicant agrees to pay the costs of preparing the record of proceedings for the project concurrent with review and consideration of the project pursuant to this division, in a form and manner specified by the lead agency for the project.
(c) (1) The Governor may certify the project for streamlining pursuant to this section if it complies with the conditions specified in subdivision (b) .
- (2) (A) Prior to certifying the project, the Governor shall make a determination that each of the conditions specified in subdivision (b) has been met. These findings are not subject to judicial review.
(B) (i) If the Governor determines that the project is eligible for streamlining pursuant to this section, he or she shall submit that determination, and any supporting information, to the Joint Legislative Budget Committee for review and concurrence or nonconcurrence.
- (ii) Within 30 days of receiving the determination, the Joint Legislative Budget Committee shall concur or nonconcur in writing on the determination.
141
Association of Environmental Professionals 2025
CEQA Statute
- (iii) If the Joint Legislative Budget Committee fails to concur or nonconcur on a determination by the Governor within 30 days of the submittal, the project is deemed to be certified.
(3) The guidelines issued pursuant to Chapter 6.5 (commencing with Section 21178) apply for the implementation of this section to the extent the guidelines are applicable and do not conflict with specific requirements of this section, including the transportation demand management program specified in subparagraph (B) of paragraph (3) of subdivision (a) .
(d) (1) Within 10 days of the Governor certifying the project pursuant to this section, the lead agency shall, at the applicant’s expense, issue a public notice in no less than 12-point type stating the following:
- “THE APPLICANT HAS ELECTED TO PROCEED UNDER SECTION 21168.6.8 OF THE PUBLIC RESOURCES CODE, WHICH PROVIDES, AMONG OTHER THINGS, THAT ANY JUDICIAL ACTION CHALLENGING THE CERTIFICATION OF THE EIR OR THE APPROVAL OF THE PROJECT DESCRIBED IN THE EIR IS SUBJECT TO THE PROCEDURES SET FORTH IN SECTION 21186.6.8 OF THE PUBLIC RESOURCES CODE. A COPY OF SECTION 21168.6.8 OF THE PUBLIC RESOURCES CODE IS INCLUDED BELOW- (2) The public notice shall be distributed by the lead agency as required for public notices issued pursuant to paragraph (3) of subdivision (b) of Section 21092.
(e) Notwithstanding any other law, the procedures set forth in subdivision shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of any environmental impact report for the project that is certified pursuant to this section or the granting of any project approvals.
(f) Rules 3.2220 to 3.2237, inclusive, of the California Rules of Court, as may be amended by the Judicial Council, shall apply to any action or proceeding brought to attack, review, set aside, void, or annul the certification of any environmental impact report for the project or granting of any project approvals to require the actions or proceeding, including any potential appeals therefrom, to be resolved, to the extent feasible, within 270 days of the filing of the certified record of proceedings with the court. On or before July 1, 2019, the Judicial Council shall amend the California Rules of Court, as necessary, to implement this subdivision.
(g) Notwithstanding any other law, the preparation and certification of the record of proceedings for the certified project shall be performed in the following manner:
(1) The lead agency for the project shall prepare the record of proceedings pursuant to this division concurrently with the administrative process.
(2) All documents and other materials placed in the record of proceedings shall be posted on, and be downloadable from, an Internet Web site maintained by the lead agency commencing with the date of the release of the draft environmental impact report.
(3) The lead agency shall make available to the public in a readily accessible electronic format the draft environmental impact report and all other documents submitted to, or relied on by, the lead agency in the preparation of the draft environmental impact report.
(4) A document prepared by the lead agency or submitted by the applicant after the date of the release of the draft environmental impact report that is a part of the record of the proceedings shall be made available to the public in a readily accessible electronic format within five business days after the document is released or received by the lead agency.
142
Association of Environmental Professionals 2025
CEQA Statute
(5) The lead agency shall encourage written comments on the project to be submitted in a readily accessible electronic format, and shall make any comment available to the public in a readily accessible electronic format within five days of its receipt.
(6) Within 14 business days after the receipt of any comment that is not in an electronic format, the lead agency shall convert that comment into a readily accessible electronic format and make it available to the public in that format.
(7) Notwithstanding paragraphs (2) to (6) , inclusive, documents submitted to or relied on by the lead agency that were not prepared specifically for the project and are copyright protected are not required to be made readily accessible in an electronic format. For those copyrightprotected documents, the lead agency shall make an index of these documents available in an electronic format no later than the date of the release of the draft environmental impact report, or within five business days if the document is received or relied on by the lead agency after the release of the draft environmental impact report. The index shall specify the libraries or lead agency offices in which hardcopies of the copyrighted materials are available for public review.
(8) The lead agency shall certify the final record of proceedings within five days after the filing of the notice required by subdivision (a) of Section 21152.
(9) Any dispute arising from the record of proceedings shall be resolved by the superior court. Unless the superior court directs otherwise, a party disputing the content of the record shall file a motion to augment the record at the time it files its initial brief.
(10) The contents of the record of proceedings shall be as set forth in subdivision (e) of Section 21167.6.
(h) The provisions of this section are severable. If any provision of this section or its application is held invalid, that invalidity shall not affect other provisions or applications that can be given effect without the invalid provision or application.
(i) (1) If the lead agency fails to certify an environmental impact report for the project before January 1, 2025, this section shall become inoperative and is repealed as of that date.
- (2) The lead agency shall notify the Secretary of State if it fails to certify the environmental impact report for the project before January 1, 2025.
(j) (1) As a condition of approval of the project, the lead agency shall require the applicant, with respect to any measures specific to the operation of the arena, to implement measures that will meet the requirements of this division by the end of the first NBA regular season or June of the first NBA regular season, whichever is later, during which an NBA team has played at the arena.
(2) To maximize public health, environmental, and employment benefits, the lead agency shall require measures that will reduce the emissions of greenhouse gases in the project area and in the neighboring communities of the arena.
(3) Not less than 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirement of paragraph (3) of subdivision (b) shall be from local, direct greenhouse gas emissions reduction measures, including, but not limited to, any of the following:
(A) Project design features or onsite reduction measures, or both design features and onsite reduction measures, that include, but are not limited to, any of the following:
- (i) Implementing project design features that enable the arena to exceed the building energy efficiency standards set forth in Part 6 of Title 24 of the California Code of Regulations, except for 50 percent of emissions reductions attributable to design features necessary to meet the LEED gold certification requirement.
143
Association of Environmental Professionals 2025
CEQA Statute
- (ii) Requiring a transportation demand management program to reduce singleoccupancy vehicular travel and vehicle miles traveled.
- (iii) Providing onsite renewable energy generation, including a solar roof on the arena with a minimum peak generation capacity of 500 kilowatts.
- (iv) Providing solar-ready roofs.
- (v) Providing cool roofs and “cool parking” promoting cool surface treatment for new parking facilities.
- (B) Off-site reduction measures in the neighboring communities, including, but not limited to, any of the following:
- (i) Temporarily expanding the capacity of a public transit line, as appropriate, to serve arena events.
- (ii) Paying its fair share of the cost of measures that expand the capacity of public transit, if appropriate, that is used by spectators attending arena events.
- (iii) Providing funding to an off-site mitigation project consisting of replacing buses, trolleys, or other transit vehicles with zero-emission vehicles.
(iv) Providing off-site safety or other improvements for bicycles, pedestrians, and transit connections.
- (v) Providing zero-emission transit buses to serve arena events and to meet other local transit needs, including senior and public school transportation services. - (vi) Undertaking or funding building retrofits to improve the energy efficiency of existing buildings.- (4) The applicant may obtain offset credits for up to 50 percent of the greenhouse gas emissions reductions necessary to achieve the requirements of paragraph (3) of subdivision (b) . The applicant shall, to the extent feasible, place the highest priority on the purchase of offset credits that produce emission reductions within the City of Inglewood or the boundaries of the South Coast Air Quality Management District. Any offset credits shall be verified by a third party accredited by the State Air Resources Board. Offset credits generated by a project located outside the United States shall not be used pursuant to this paragraph.
(k) As a condition of approval of the project, the lead agency shall require the applicant, in consultation with the South Coast Air Quality Management District, to implement measures that will achieve criteria pollutant and toxic air contaminant reductions over and above any emission reductions required by other laws or regulations in communities surrounding the project consistent with emission reduction measures that may be identified for those communities pursuant to Section 44391.2 of the Health and Safety Code.
(1) At a minimum, these measures shall achieve reductions of a minimum of 400 tons of oxides of nitrogen and 10 tons of PM2.5, as defined in Section 39047.2 of the Health and Safety Code, over 10 years following the commencement of construction of the project. Of these amounts, reductions of a minimum of 130 tons of oxides of nitrogen and 3 tons of PM2.5 shall be achieved within the first year following commencement of construction of the project. The reductions required pursuant to this paragraph are in addition to any other requirements imposed by other laws.
(2) If the project applicant can demonstrate and verify to the South Coast Air Quality Management District that it has invested at least thirty million dollars ($30,000,000) to achieve the requirements of this subdivision, the requirements of this subdivision shall be deemed met, so long as one-half of the reductions set forth in paragraph (1) are met.
144
Association of Environmental Professionals 2025
CEQA Statute
(3) Greenhouse gas emissions reductions achieved pursuant to this subdivision shall count toward the applicant’s obligations under paragraph (3) of subdivision (j) .
(l) This section does not apply to a project that proposes the construction of a new gambling establishment, as defined in Section 19805 of the Business and Professions Code or Section 337 of the Penal Code.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — CEQA Statute and Guidelines (2025 consolidated text)
- California Environmental Quality Act (CEQA) Statute and Guidel…
- www.califaep.org
- Contents
- OVERVIEW OF THE ASSOCIATION OF ENVIRONMENTAL PROFESSIONALS
- AEP’s Mission is to:
- NAEP Affiliation
- Full (Individual) Membership
- Agency/Corporate Membership
- Emeritus Membership
- Young Professionals Membership
- Student Membership
- Web Site
- Environmental Monitor
- Environmental Assessor
- Local Chapter Activities
- Environmental Services Bulletin
- Annual State Conference
- Professional Practice Insurance Discounts
- Biannual CEQA Workshops
- Membership Certificate
- Annual CEQA Handbook
- Legislative Activities
- Regional Area Support
- Professional Award Program
- Association of Environmental Professionals Continuing Educatio…
- Member Services
- Special Committees
- Professional Discounts
- SUMMARY OF KEY 2024 CEQA COURT CASES
- West Adams Heritage Assoc. v. City of Los Angeles (Oct. 31, 20…
- Gooden v. County of Los Angeles (Oct. 24, 2024) Cal.App.5th
- Bonta v. County of Lake (Oct. 23, 2024) Cal.App.5th
- Santa Clarita Organization for Planning the Environment v. Cou…
- Save Our Capitol! v. Department of General Services (Oct. 9, 2…
- Yolo Land and Water Defense v. County of Yolo (Oct. 3, 2024) 1…
- Friends of the South Fork Gualala v. Department of Forestry an…
- California Natural Gas Vehicle Coalition v. State Air Resource…
- Upland Community First v. City of Upland (Sept. 13, 2024) 105 …
- Sunflower Alliance v. California Dept. of Conservation (Sept. …
- Westside Los Angeles Neighbors Network v. City of Los Angeles …
- Center for Biological Diversity v. County of San Benito (Aug. …
- Nassiri v. City of Lafayette (Sept. 18, 2024) 103 Cal.App.5th …
- Make UC a Good Neighbor v. The Regents of the University of Ca…
- Save the Capitol, Save the Trees v. Department of General Serv…
- Vichy Springs Resort, Inc. v. City of Ukiah (March 29. 2024) 1…
- V Lions Farming, LLC v. County of Kern (March 7, 2024) 100 Cal…
- Hilltop Group, Inc. v. County of San Diego (Feb. 16, 2024) 99 …
- Natural Resources Defense Council v. City of Los Angeles (Jan.…
- Guerrero v. City of Los Angeles (Jan. 17, 2024) 98 Cal.App.5th…
- Planning and Conservation League v. Dept. of Water Resources (…
- SUMMARY OF KEY 2024 CEQA LEGISLATION
- AB 1359 (Chapter 678, Statutes of 2024) [Urgency bill: took ef…
- AB 1413 (Chapter 265, Statutes of 2024)
- AB 2085 (Chapter 820, Statutes of 2024)
- AB 2091 (Chapter 377, Statutes of 2024)
- AB 2199 (Chapter 271, Statutes of 2024)
- AB 2503 (Chapter 718, Statutes of 2024)
- AB 2553 (Chapter 275, Statutes of 2024)
- AB 3007 (Chapter 583, Statutes of 2024)
- AB 3057 (Chapter 210, Statutes of 2024)
- AB 3122 (Chapter 754, Statutes of 2024)
- AB 3227 (Chapter 761, Statutes of 2024)
- AB 3265 (Bryan) (Chapter 255, Statutes of 2024)
- SB 174 (Chapter 74, Statutes of 2024)
- SB 312 (Weiner) (Chapter 284, Statutes of 2024)
- SB 768 (Caballero) (Chapter 773, Statutes of 2024)
- SB 1123 (Chapter 294, Statutes of 2024)
- SB 1342 (Chapter 794, Statutes of 2024)
- SB 1361 (Chapter 188, Statutes of 2024)
- SB 1420 (Chapter 608, Statutes of 2024)
- Changes Made to CEQA in 2024
- CALIFORNIA ENVIRONMENTAL QUALITY ACT CALIFORNIA PUBLIC RESOURC…
- Chapter 1: Policy
- § 21000. LEGISLATIVE INTENT
- § 21001. ADDITIONAL LEGISLATIVE INTENT
- § 21001.1. REVIEW OF PUBLIC AGENCY PROJECTS
- § 21002. APPROVAL OF PROJECTS; FEASIBLE ALTERNATIVE OR MITIGAT…
- § 21002.1. USE OF ENVIRONMENTAL IMPACT REPORTS; POLICY
- § 21003. PLANNING AND ENVIRONMENTAL REVIEW PROCEDURES; DOCUMEN…
- § 21003.1. ENVIRONMENTAL EFFECTS OF PROJECTS; COMMENTS FROM PU…
- § 21004. MITIGATING OR AVOIDING A SIGNIFICANT EFFECT; POWERS O…
- § 21005. INFORMATION DISCLOSURE PROVISIONS; NONCOMPLIANCE; PRE…
- § 21006. ISSUANCE OF PERMITS, LICENSES, CERTIFICATES OR OTHER …
- Chapter 2: Short Title
- § 21050. CITATION
- Chapter 2.5: Definitions
- § 21060. APPLICATION OF DEFINITIONS
- § 21060.1. AGRICULTURAL LAND
- § 21060.2.
- § 21060.3. EMERGENCY
- § 21060.5. ENVIRONMENT
- § 21061. ENVIRONMENTAL IMPACT REPORT
- § 21061.1. FEASIBLE
- § 21061.2. LAND EVALUATION AND SITE ASSESSMENT
- § 21061.3. INFILL SITE
- § 21062. LOCAL AGENCY
- § 21063. PUBLIC AGENCY
- § 21064. NEGATIVE DECLARATION
- § 21064.3. MAJOR TRANSIT STOP
- § 21064.5. MITIGATED NEGATIVE DECLARATION
- § 21065. PROJECT
- § 21065.3. PROJECT-SPECIFIC EFFECT
- § 21065.5. GEOTHERMAL EXPLORATORY PROJECT
- § 21066. PERSON
- § 21067. LEAD AGENCY
- § 21068. SIGNIFICANT EFFECT ON THE ENVIRONMENT
- § 21068.5. TIERING OR TIER
- § 21069. RESPONSIBLE AGENCY
- § 21070. TRUSTEE AGENCY
- § 21071. URBANIZED AREA; DEFINITION
- § 21072. QUALIFIED URBAN USE; DEFINITION
- § 21073.
- § 21074.
- Chapter 2.6: General
- § 21080. DIVISION APPLICATION TO DISCRETIONARY PROJECTS; NONAP…
- § 21080.01. CALIFORNIA MEN’S COLONY WEST FACILITY IN SAN LUIS …
- § 21080.02. KINGS COUNTY; VICINITY OF CORCORAN; NEW PRISON FAC…
- § 21080.03. KINGS AND AMADOR (IONE) COUNTIES; PRISONS; APPLICA…
- § 21080.04. ROCKTRAM-KRUG PASSENGER RAIL SERVICE PROJECT; APPL…
- § 21080.05. SAN FRANCISCO PENINSULA COMMUTE SERVICE PROJECT BE…
- § 21080.07. RIVERSIDE AND DEL NORTE COUNTIES; PLANNING AND CON…
- § 21080.09. PUBLIC HIGHER EDUCATION; CAMPUS LOCATION; LONG-RAN…
- § 21080.1. ENVIRONMENTAL IMPACT REPORT OR NEGATIVE DECLARATION…
- § 21080.2. ISSUANCE OF LEASE, PERMIT, LICENSE, CERTIFICATE OR …
- § 21080.3. CONSULTATION WITH RESPONSIBLE AGENCIES; ASSISTANCE …
- § 21080.3.1.
- § 21080.3.2.
- § 21080.4. ENVIRONMENTAL IMPACT REPORT; REQUIREMENT DETERMINED…
- § 21080.5. PLAN OR OTHER WRITTEN DOCUMENTATION; SUBMISSION IN …
- § 21080.8. APPLICATION OF DIVISION; CONVERSION OF EXISTING REN…
- § 21080.9. LOCAL COASTAL PROGRAMS OR LONG-RANGE LAND USE DEVEL…
- § 21080.10. APPLICATION OF DIVISION; GENERAL PLANS; LOW- OR MO…
- § 21080.11. APPLICATION OF DIVISION; SETTLEMENTS BY STATE LAND…
- § 21080.12.
- § 21080.13. RAILROAD GRADE SEPARATION PROJECTS; APPLICATION OF…
- ~~ § 21080.14. ~~
- § 21080.17. APPLICATION OF DIVISION TO ORDINANCES IMPLEMENTING…
- § 21080.18. APPLICATION OF DIVISION TO CLOSING OF PUBLIC SCHOO…
- § 21080.19. RESTRIPING OF STREETS OR HIGHWAYS; APPLICATION OF …
- § 21080.20 TRANSPORTATION PLANS, PEDESTRIAN PLANS, AND BICYCLE…
- § 21080.21. APPLICATION OF DIVISION TO PUBLIC RIGHT-OF-WAY PIP…
- § 21080.22. LOCAL GOVERNMENTS; PREPARATION OF GENERAL PLAN AME…
- § 21080.23. PIPELINE PROJECTS; APPLICATION OF DIVISION
- § 21080.24. PERMITS; ISSUANCE, MODIFICATION, AMENDMENT, OR REN…
- § 21080.25
- § 21080.26. FLUORIDATION; APPLICATION OF DIVISION; MINOR ALTER…
- ~~ § 21080.27. ~~
- ~~(1) “Eligible public agency” means any of the following:~~
- § 21080.28.
- § 21080.28.5.
- § 21080.29. LA PLAYA PROJECT; APPLICATION OF DIVISION
- § 21080.31.
- § 21080.32. EXEMPTION OF SPECIFIED ACTIONS BY PUBLICLY OWNED T…
- § 21080.33. EMERGENCY PROJECTS TO MAINTAIN, REPAIR OR RESTORE …
- § 21080.35. CARRYING OUT OR APPROVING A PROJECT; DEFINITION
- § 21080.35.[1]
- § 21080.40.
- § 21080.42.
- § 21080.47
- § 21080.50
- § 21080.51
- § 21080.56.
- § 21080.58.
- § 21080.61.
- § 21081. NECESSARY FINDINGS WHERE ENVIRONMENTAL IMPACT REPORT …
- § 21081.2 EXCEPTION TO FINDINGS FOR INFILL RESIDENTIAL PROJECTS
- § 21081.3. AESTHETIC IMPACTS
- (b) Subdivision (a) shall not apply to either of the following:
- § 21081.5. FEASIBILITY OF MITIGATION MEASURES OR PROJECT ALTER…
- § 21081.6. FINDINGS OR NEGATIVE DECLARATIONS; REPORTING OR MON…
- § 21081.7. TRANSPORTATION INFORMATION; SUBMISSION OF REPORT TO…
- § 21082. PUBLIC AGENCIES; ADOPTION OF OBJECTIVES, CRITERIA AND…
- § 21082.1. DRAFT ENVIRONMENTAL IMPACT REPORT, ENVIRONMENTAL IM…
- § 21082.2. SIGNIFICANT EFFECT ON ENVIRONMENT; DETERMINATION; E…
- § 21082.3.
- § 21082.4.
- § 21083. OFFICE OF PLANNING AND RESEARCH; PREPARATION AND DEVE…
- § 21083.01. GUIDELINES AMENDMENTS; FIRE HAZARD
- § 21083.05.
- § 21083.09.
- § 21083.1. LEGISLATIVE INTENT; INTERPRETATION BY COURTS
- § 21083.2. ARCHAEOLOGICAL RESOURCES; DETERMINATION OF EFFECT O…
- § 21083.3. APPLICATION OF DIVISION TO APPROVAL OF SUBDIVISION …
- § 21083.4. COUNTIES; CONVERSION OF OAK WOODLANDS; MITIGATION A…
- § 21083.5. ENVIRONMENTAL IMPACT STATEMENT OR REPORT; SUBMISSIO…
- § 21083.6. COMBINED ENVIRONMENTAL IMPACT REPORT AND STATEMENT;…
- § 21083.7. USE OF IMPACT STATEMENT AS THE IMPACT REPORT; CONSU…
- § 21083.8.1. REUSE PLANS
- § 21083.9. SCOPING MEETINGS
- § 21084. LIST OF EXEMPT CLASSES OF PROJECTS; PROJECTS DAMAGING…
- § 21084.1. HISTORICAL RESOURCE; SUBSTANTIAL ADVERSE CHANGE
- § 21084.2.
- § 21084.3.
- § 21085.
- § 21085.2
- § 21086. ADDITION OR DELETION OF EXEMPT CLASSES OF PROJECTS; P…
- § 21088. DISTRIBUTION OF GUIDELINES, AMENDMENTS AND CHANGES; N…
- § 21089. FEES
- § 21090. REDEVELOPMENT PLAN DEEMED SINGLE PROJECT
- § 21090.1. GEOTHERMAL EXPLORATORY PROJECT DEEMED SEPARATE AND …
- § 21091. DRAFT ENVIRONMENTAL IMPACT REPORTS AND NEGATIVE DECLA…
- § 21091.5. PUBLIC REVIEW PERIOD FOR DRAFT ENVIRONMENTAL IMPACT…
- § 21092. PUBLIC NOTICE OF PREPARATION OF ENVIRONMENTAL IMPACT …
- § 21092.1. ADDITION OF NEW INFORMATION; NOTICE AND CONSULTATION
- § 21092.2. REQUESTS FOR CERTAIN NOTICES
- § 21092.3. POSTING OF CERTAIN NOTICES
- § 21092.4. CONSULTATION WITH TRANSPORTATION PLANNING AGENCIES …
- § 21092.5. PROPOSED RESPONSE TO PUBLIC AGENCY COMMENTS RECEIVE…
- § 21092.6. APPLICATION OF GOVT. C. § 65962.5; DUTIES OF LEAD A…
- § 21093. LEGISLATIVE FINDINGS AND DECLARATION; PUBLIC AGENCIES…
- § 21094. LATER PROJECTS; TIERED ENVIRONMENTAL IMPACT REPORTS; …
- § 21094.5.
- § 21094.5.5.
- § 21095. AMENDMENT TO STATE GUIDELINES TO PROVIDE OPTIONAL MET…
- § 21096. AIRPORT-RELATED SAFETY HAZARDS AND NOISE PROBLEMS; PR…
- § 21098. LOW-LEVEL FLIGHT PATH; MILITARY IMPACT ZONE; SPECIAL …
- Chapter 2.7: Modernization of Transportation Analysis for Tran…
- § 21099.
- § 21099.5.
- Chapter 3: State Agencies, Boards and Commissions
- § 21100. ENVIRONMENTAL IMPACT REPORT ON PROPOSED STATE PROJECT…
- § 21100.1. INFORMATION REQUIRED IN CERTAIN ENVIRONMENTAL IMPAC…
- § 21100.2. LEASES, PERMITS, LICENSES, CERTIFICATES AND OTHER E…
- § 21100.2.
- § 21101. ENVIRONMENTAL IMPACT REPORT ON PROPOSED FEDERAL PROJE…
- § 21102. REQUEST FOR OR AUTHORIZATION OF EXPENDITURE OF FUNDS;…
- § 21104. STATE LEAD AGENCY; CONSULTATIONS PRIOR TO COMPLETION …
- § 21104.2. CONSULTATION AND FINDINGS; EFFECT OF PROJECTS ON TH…
- § 21105. ENVIRONMENTAL IMPACT REPORT AND COMMENTS AS PART OF R…
- § 21106. REQUEST OF FUNDS TO PROTECT ENVIRONMENT
- § 21108. STATE AGENCY, BOARD OR COMMISSION; APPROVAL OF DETERM…
- Chapter 4: Local Agencies
- § 21150. ENVIRONMENTAL IMPACT REPORT REQUIRED BEFORE ALLOCATIO…
- § 21151. LOCAL AGENCIES; PREPARATION AND COMPLETION OF IMPACT …
- § 21151.1. WASTE-BURNING PROJECTS; LAND DISPOSAL FACILITIES, A…
- § 21151.2. SCHOOL SITE PROPOSED ACQUISITION OR ADDITION; NOTIC…
- § 21151.4. CONSTRUCTION OR ALTERATION OF FACILITY WITHIN ONE-F…
- § 21151.5. TIME LIMITS FOR PREPARATION OF ENVIRONMENTAL IMPACT…
- § 21151.7. PREPARATION AND CERTIFICATION OF COMPLETION OF ENVI…
- § 21151.8. SCHOOLSITE ACQUISITION OR CONSTRUCTION; APPROVAL OF…
- § 21151.9. PROJECTS SUBJECT TO THIS DIVISION; COMPLIANCE REQUI…
- § 21152. LOCAL AGENCY; APPROVAL OR DETERMINATION TO CARRY OUT …
- § 21152.1. LOCAL AGENCY; EXEMPT HOUSING PROJECTS; NOTICE FILIN…
- § 21153. LOCAL LEAD AGENCY; CONSULTATIONS PRIOR TO COMPLETION …
- § 21154. ISSUANCE OF PROJECT ORDER BY STATE; EFFECT ON IMPACT …
- Chapter 4.2: Implementation of the Sustainable Communities Str…
- § 21155.
- § 21155. 1.
- § 21155.2.
- § 21155.3
- § 21155.4
- Chapter 4.3: Housing Sustainability Districts
- § 21155.10
- § 21155.11
- Chapter 4.5: Streamlined Environmental Review
- Article 1: Findings
- § 21156. LEGISLATIVE INTENT
- Article 2: Master Environmental Impact Report
- § 21157. PREPARATION; CONTENT; FEE PROGRAM
- § 21157.1. REVIEW OF SUBSEQUENT PROJECTS DESCRIBED IN REPORT; …
- § 21157.5. MITIGATED NEGATIVE DECLARATIONS; PREPARATION; CONDI…
- § 21157.6. LIMITATION PERIOD ON USE OF ENVIRONMENTAL IMPACT RE…
- § 21157.7. IMPROVEMENTS TO ROADWAY SEGMENTS OF HIGHWAY 99; USE…
- Article 3: Focused Environmental Impact Report
- § 21158. PURPOSE; CONTENT; ADDITIONAL SIGNIFICANT EFFECT ON TH…
- § 21158.1. REGULATORY PROGRAMS CERTIFIED UNDER PUBLIC RESOURCE…
- § 21158.5. MULTIPLE-FAMILY RESIDENTIAL DEVELOPMENT OF NOT MORE…
- Article 4: Expedited Environmental Review for Environmentally …
- § 21159. RULE OR REGULATION ADOPTION; ENVIRONMENTAL ANALYSIS; …
- § 21159.1. UTILIZATION OF FOCUSED ENVIRONMENTAL IMPACT REPORT;…
- § 21159.2. NEGATIVE DECLARATION; MITIGATED NEGATIVE DECLARATIO…
- § 21159.3. DEADLINES FOR PREPARATION OF REPORT
- § 21159.4. AGENCIES; ARTICLE APPLICATION
- Article 5: Public Assistance Program
- § 21159.9. IMPLEMENTATION OF PROGRAM
- Article 6: Special Review of Housing Projects
- § 21159.20. DEFINITIONS
- § 21159.21. CRITERIA TO QUALIFY FOR HOUSING PROJECT EXEMPTIONS
- § 21159.22. AGRICULTURAL EMPLOYEE HOUSING EXEMPTION
- § 21159.23. LOW-INCOME HOUSING EXEMPTION
- § 21159.24. INFILL HOUSING EXEMPTION
- § 21159.25. EXEMPTION: RESIDENTIAL OR MIXED-USE HOUSING PROJECTS
- § 21159.26. REDUCTIONS IN HOUSING UNITS AS MITIGATION DISCOURA…
- § 21159.27. PROHIBITION AGAINST PIECEMEALING TO QUALIFY FOR EX…
- § 21159.28.
- Chapter 5: Submission of Information
- § 21160. APPLICATION FOR LEASE, PERMIT, LICENSE, ETC.; DATA AN…
- § 21161. COMPLETION OF IMPACT REPORT; NOTICE; VALIDITY OF PROJ…
- § 21163.
- § 21163.1.
- § 21163.2.
- § 21163.3.
- § 21163.4.
- Chapter 6: Limitations
- § 21165. LEAD AGENCY; PREPARATION OF IMPACT REPORT
- § 21166. SUBSEQUENT OR SUPPLEMENTAL IMPACT REPORT; CONDITIONS
- § 21166.1. EFFECT OF PREPARATION OF IMPACT REPORT BY LEAD AGENCY
- § 21166.2.
- § 21167. COMMENCEMENT OF ACTIONS OR PROCEEDINGS; TIME
- § 21167.1. PREFERENTIAL HEARING OR OTHER CIVIL ACTIONS; DESIGN…
- § 21167.2. FAILURE TO COMMENCE ACTION OR PROCEEDING WITHIN TIM…
- § 21167.3. ASSUMPTION THAT IMPACT REPORT OR NEGATIVE DECLARATI…
- § 21167.4. MANDATE PROCEEDING ALLEGING NONCOMPLIANCE WITH DIVI…
- § 21167.5. PROOF OF SERVICE; FILING WITH INITIAL PLEADING
- § 21167.6. RECORD OF PROCEEDINGS; CLERK’S TRANSCRIPT ON APPEAL…
- § 21167.6.2.
- § 21167.6.5. SERVICE OF REAL PARTY IN INTEREST; LISTING AND NO…
- § 21167.7. COPY OF PLEADINGS TO ATTORNEY GENERAL; GRANTING OF …
- § 21167.8. SETTLEMENT MEETING; PRESETTLEMENT AND SETTLEMENT ST…
- § 21167.8.
- § 21167.9.
- § 21167.10.
- § 21168. REVIEW OF DETERMINATION; FINDING OR DECISION OF PUBLI…
- § 21168.5. ABUSE OF DISCRETION
- § 21168.6. MANDATE TO PUBLIC UTILITIES COMMISSION; SUPREME COU…
- § 21168.6.6.
- § 21168.6.7. OAKLAND SPORTS AND MIXED-USE PROJECT
- § 21168.6.8. SPORTS AND ENTERTAINMENT PROJECT
- § 21168.6.9.
- § 21168.7. DECLARATION OF EXISTING LAW
- § 21168.9. PUBLIC AGENCY ACTIONS; NONCOMPLIANCE WITH DIVISION;…
- § 21169. VALIDATION OF PROJECTS.
- § 21169.11.
- § 21173. SEVERABILITY
- § 21174. CONSTRUCTION OF DIVISION; ENFORCEMENT OF OTHER PROVIS…
- § 21177. PRESENTATION OF GROUNDS FOR NONCOMPLIANCE; OBJECTIONS…
- Chapter 6.5: Jobs and Economic Improvement through Environment…
- § 21178.
- § 21180.
- § 21181.
- § 21182.
- § 21183.
- § 21183.5.
- § 21183.6.
- § 21184.
- § 21184.5.
- § 21184.7.
- § 21185.
- § 21186.
- § 21187.
- § 21187.5
- § 21188.
- § 21189.
- § 21189.1.
- § 21189.3
- Chapter 6.9: City of San Diego: Old Town Center Redevelopment
- § 21189.70
- § 21189.70.1.
- § 21189.70.2.
- § 21189.70.3.
- § 21189.70.4.
- § 21189.70.5.
- § 21189.70.6.
- § 21189.70.7.
- § 21189.70.8.
- § 21189.70.9.
- § 21189.70.10.
- § 21189.80.
- § 21189.81.
- § 21189.81.1.
- § 21189.82.
- § 21189.83.
- § 21189.84.
- § 21189.85.
- § 21189.86.
- § 21189.87.
- § 21189.88.
- § 21189.89.
- § 21189.90.
- § 21189.91.
- CHAPTER 3: GUIDELINES FOR IMPLEMENTATION OF THE CALIFORNIA ENV…
- AS AMENDED DECEMBER 28, 2018
- Article 1. General
- 15000. AUTHORITY
- 15001. SHORT TITLE
- 15002. GENERAL CONCEPTS
- 15003. POLICIES
- 15004. TIME OF PREPARATION
- 15005. TERMINOLOGY
- 15006. REDUCING DELAY AND PAPERWORK
- 15007. AMENDMENTS
- Article 2. General Responsibilities
- 15020. GENERAL
- 15021. DUTY TO MINIMIZE ENVIRONMENTAL DAMAGE AND BALANCE COMPE…
- 15022. PUBLIC AGENCY IMPLEMENTING PROCEDURES
- 15023. OFFICE OF PLANNING AND RESEARCH (OPR)
- 15024. SECRETARY FOR RESOURCES
- 15025. DELEGATION OF RESPONSIBILITIES
- Article 3. Authorities Granted to Public Agencies by CEQA
- 15040. AUTHORITY PROVIDED BY CEQA
- 15041. AUTHORITY TO MITIGATE
- 15042. AUTHORITY TO DISAPPROVE PROJECTS
- 15043. AUTHORITY TO APPROVE PROJECTS DESPITE SIGNIFICANT EFFECTS
- 15044. AUTHORITY TO COMMENT
- 15045. FEES
- Article 4. Lead Agency
- 15050. LEAD AGENCY CONCEPT
- 15051. CRITERIA FOR IDENTIFYING THE LEAD AGENCY
- 15052. SHIFT IN LEAD AGENCY DESIGNATION
- 15053. DESIGNATION OF LEAD AGENCY BY THE OFFICE OF PLANNING AN…
- Article 5. Preliminary Review of Projects and Conduct of Initi…
- 15060. PRELIMINARY REVIEW
- 15060.5. PREAPPLICATION CONSULTATION
- 15061. REVIEW FOR EXEMPTION
- 15062. NOTICE OF EXEMPTION
- 15063. INITIAL STUDY
- 15064. DETERMINING THE SIGNIFICANCE OF THE ENVIRONMENTAL EFFEC…
- SECTION 15064.3. DETERMINING THE SIGNIFICANCE OF TRANSPORTATIO…
- 15064.4. DETERMINING THE SIGNIFICANCE OF IMPACTS FROM GREENHOU…
- 15064.5. DETERMINING THE SIGNIFICANCE OF IMPACTS TO ARCHAEOLOG…
- 15064.7. THRESHOLDS OF SIGNIFICANCE.
- 15065. MANDATORY FINDINGS OF SIGNIFICANCE
- Article 6. Negative Declaration Process
- 15070. DECISION TO PREPARE A NEGATIVE OR MITIGATED NEGATIVE DE…
- 15071. CONTENTS
- 15072. NOTICE OF INTENT TO ADOPT A NEGATIVE DECLARATION OR MIT…
- 15073. PUBLIC REVIEW OF A PROPOSED NEGATIVE DECLARATION OR MIT…
- 15073.5. RECIRCULATION OF A NEGATIVE DECLARATION PRIOR TO ADOP…
- 15074. CONSIDERATION AND ADOPTION OF A NEGATIVE DECLARATION OR…
- 15074.1. SUBSTITUTION OF MITIGATION MEASURES IN A PROPOSED MIT…
- 15075. NOTICE OF DETERMINATION ON A PROJECT FOR WHICH A PROPOS…
- Article 7. EIR Process
- 15080. GENERAL
- 15081. DECISION TO PREPARE AN EIR
- 15081.5. EIRS REQUIRED BY STATUTE
- 15082. NOTICE OF PREPARATION AND DETERMINATION OF SCOPE OF EIR
- 15083. EARLY PUBLIC CONSULTATION
- 15084. PREPARING THE DRAFT EIR
- 15085. NOTICE OF COMPLETION
- 15086. CONSULTATION CONCERNING DRAFT EIR
- 15087. PUBLIC REVIEW OF DRAFT EIR
- 15088. EVALUATION OF AND RESPONSE TO COMMENTS
- 15088.5. RECIRCULATION OF AN EIR PRIOR TO CERTIFICATION
- 15089. PREPARATION OF FINAL EIR
- 15090. CERTIFICATION OF THE FINAL EIR
- 15091. FINDINGS
- 15092. APPROVAL
- 15093. STATEMENT OF OVERRIDING CONSIDERATIONS
- 15094. NOTICE OF DETERMINATION
- 15095. DISPOSITION OF A FINAL EIR
- 15096. PROCESS FOR A RESPONSIBLE AGENCY
- 15097. MITIGATION MONITORING OR REPORTING.
- Article 8. Time Limits
- 15100. GENERAL
- 15101. REVIEW OF APPLICATION FOR COMPLETENESS
- 15102. INITIAL STUDY
- 15103. RESPONSE TO NOTICE OF PREPARATION
- 15104. CONVENING OF MEETINGS
- 15105. PUBLIC REVIEW PERIOD FOR A DRAFT EIR OR A PROPOSED NEGA…
- 15107. COMPLETION OF NEGATIVE DECLARATION
- 15108. COMPLETION AND CERTIFICATION OF EIR
- 15109. SUSPENSION OF TIME PERIODS
- 15110. PROJECTS WITH FEDERAL INVOLVEMENT
- 15111. PROJECTS WITH SHORT TIME PERIODS FOR APPROVAL
- 15112. STATUTES OF LIMITATIONS
- Article 9. Contents of Environmental Impact Reports
- 15120. GENERAL
- 15121. INFORMATIONAL DOCUMENT
- 15122. TABLE OF CONTENTS OR INDEX
- 15123. SUMMARY
- 15124. PROJECT DESCRIPTION
- 15125. ENVIRONMENTAL SETTING
- 15126. CONSIDERATION AND DISCUSSION OF ENVIRONMENTAL IMPACTS
- 15126.2 CONSIDERATION AND DISCUSSION OF SIGNIFICANT ENVIRONMEN…
- 15126.4 CONSIDERATION AND DISCUSSION OF MITIGATION MEASURES PR…
- 15126.6. CONSIDERATION AND DISCUSSION OF ALTERNATIVES TO THE P…
- 15127. LIMITATIONS ON DISCUSSION OF ENVIRONMENTAL IMPACT
- 15128. EFFECTS NOT FOUND TO BE SIGNIFICANT
- 15129. ORGANIZATIONS AND PERSONS CONSULTED
- 15130. DISCUSSION OF CUMULATIVE IMPACTS
- 15131. ECONOMIC AND SOCIAL EFFECTS
- 15132. CONTENTS OF FINAL ENVIRONMENTAL IMPACT REPORT
- Article 10. Considerations in Preparing EIRs and Negative Decl…
- 15140. WRITING
- 15141. PAGE LIMITS
- 15142. INTERDISCIPLINARY APPROACH
- 15143. EMPHASIS
- 15144. FORECASTING
- 15145. SPECULATION
- 15146. DEGREE OF SPECIFICITY
- 15147. TECHNICAL DETAIL
- 15148. CITATION
- 15149. USE OF REGISTERED PROFESSIONALS IN PREPARING EIRS
- 15150. INCORPORATION BY REFERENCE
- 15151. STANDARDS FOR ADEQUACY OF AN EIR
- 15152. TIERING
- 15153. USE OF AN EIR FROM AN EARLIER PROJECT
- 15154. PROJECTS NEAR AIRPORTS
- 15155. WATER SUPPLY ANALYSIS; CITY OR COUNTY CONSULTATION WITH…
- Article 11. Types of EIRs
- 15160. GENERAL
- 15161. PROJECT EIR
- 15162. SUBSEQUENT EIRS AND NEGATIVE DECLARATIONS
- 15163. SUPPLEMENT TO AN EIR
- 15164. ADDENDUM TO AN EIR OR NEGATIVE DECLARATION
- 15165. MULTIPLE AND PHASED PROJECTS
- 15166. EIR AS PART OF A GENERAL PLAN
- 15167. STAGED EIR
- 15168. PROGRAM EIR
- 15169. MASTER ENVIRONMENTAL ASSESSMENT
- 15170. JOINT EIR-EIS
- Article 11.5 Master Environmental Impact Report
- 15175. MASTER EIR
- 15176. CONTENTS OF A MASTER EIR
- 15177. SUBSEQUENT PROJECTS WITHIN THE SCOPE OF THE MEIR
- 15178. SUBSEQUENT PROJECTS IDENTIFIED IN THE MEIR
- 15179. LIMITATIONS ON THE USE OF THE MASTER EIR
- 15179.5. FOCUSED EIRS AND SMALL PROJECTS
- Article 12. Special Situations
- 15180. REDEVELOPMENT PROJECTS
- 15182. PROJECTS PURSUANT TO A SPECIFIC PLAN
- 15183. PROJECTS CONSISTENT WITH A COMMUNITY PLAN OR ZONING
- 15183.3 STREAMLINING FOR INFILL PROJECTS
- 15183.5. TIERING AND STREAMLINING THE ANALYSIS OF GREENHOUSE G…
- 15184. STATE MANDATED LOCAL PROJECTS
- 15185. ADMINISTRATIVE APPEALS
- 15186. SCHOOL FACILITIES
- 15187. ENVIRONMENTAL REVIEW OF NEW RULES AND REGULATIONS
- 15188. FOCUSED EIR FOR POLLUTION CONTROL EQUIPMENT
- 15189. COMPLIANCE WITH PERFORMANCE STANDARD OR TREATMENT REQUI…
- 15190. DEADLINES FOR COMPLIANCE WITH SECTIONS 15188 AND 15189
- 15190.5. DEPARTMENT OF DEFENSE NOTIFICATION REQUIREMENT
- Article 12.5 Exemptions for Agricultural Housing, Affordable H…
- 15191. DEFINITIONS
- 15192. THRESHOLD REQUIREMENTS FOR EXEMPTIONS FOR AGRICULTURAL …
- 15193. AGRICULTURAL HOUSING EXEMPTION
- 15194. AFFORDABLE HOUSING EXEMPTION
- 15195. RESIDENTIAL INFILL EXEMPTION
- 15196. NOTICE OF EXEMPTION FOR AGRICULTURAL HOUSING, AFFORDABL…
- Article 13. Review and Evaluation of EIRs and Negative Declara…
- 15200. PURPOSES OF REVIEW
- 15201. PUBLIC PARTICIPATION
- 15202. PUBLIC HEARINGS
- 15203. ADEQUATE TIME FOR REVIEW AND COMMENT
- 15204. FOCUS OF REVIEW
- 15205. REVIEW BY STATE AGENCIES
- 15206. PROJECTS OF STATEWIDE, REGIONAL, OR AREAWIDE SIGNIFICANCE
- 15207. FAILURE TO COMMENT
- 15208. RETENTION AND AVAILABILITY OF COMMENTS
- 15209. COMMENTS ON INITIATIVE OF PUBLIC AGENCIES
- Article 14. Projects Also Subject to the National Environmenta…
- 15220. GENERAL
- 15221. NEPA DOCUMENT READY BEFORE CEQA DOCUMENT
- 15222. PREPARATION OF JOINT DOCUMENTS
- 15223. CONSULTATION WITH FEDERAL AGENCIES
- 15224. TIME LIMITS
- 15225. CIRCULATION OF DOCUMENTS
- 15226. JOINT ACTIVITIES
- 15227. STATE COMMENTS ON A FEDERAL PROJECT
- 15228. WHERE FEDERAL AGENCY WILL NOT COOPERATE
- 15229. BASELINE ANALYSIS FOR MILITARY BASE REUSE PLAN EIRS
- Article 15. Litigation
- 15230. TIME LIMITS AND CRITERIA
- 15231. ADEQUACY OF EIR OR NEGATIVE DECLARATION FOR USE BY RESP…
- 15232. REQUEST FOR HEARING
- 15233. CONDITIONAL PERMITS
- SECTION 15234. REMAND
- Article 16. EIR Monitor
- SECTION 15240
- 15240. EIR MONITOR
- Article 17. Exemption for Certified State Regulatory Programs
- 15250. GENERAL
- 15251. LIST OF CERTIFIED PROGRAMS
- 15252. SUBSTITUTE DOCUMENT
- 15253. USE OF AN EIR SUBSTITUTE BY A RESPONSIBLE AGENCY
- Article 18. Statutory Exemptions
- 15260. GENERAL
- 15261. ONGOING PROJECT
- 15262. FEASIBILITY AND PLANNING STUDIES
- 15263. DISCHARGE REQUIREMENTS
- 15264. TIMBERLAND PRESERVES
- 15265. ADOPTION OF COASTAL PLANS AND PROGRAMS
- 15266. GENERAL PLAN TIME EXTENSION
- 15267. FINANCIAL ASSISTANCE TO LOW OR MODERATE INCOME HOUSING
- 15268. MINISTERIAL PROJECTS
- 15269. EMERGENCY PROJECTS
- 15270. PROJECTS WHICH ARE DISAPPROVED
- 15271. EARLY ACTIVITIES RELATED TO THERMAL POWER PLANTS
- 15272. OLYMPIC GAMES
- 15273. RATES, TOLLS, FARES, AND CHARGES
- 15274. FAMILY DAY CARE HOMES
- 15275. SPECIFIED MASS TRANSIT PROJECTS
- 15276. TRANSPORTATION IMPROVEMENT AND CONGESTION MANAGEMENT PR…
- 15277. PROJECTS LOCATED OUTSIDE CALIFORNIA
- 15278. APPLICATION OF COATINGS
- 15281. AIR QUALITY PERMITS
- 15282. OTHER STATUTORY EXEMPTIONS
- 15283. HOUSING NEEDS ALLOCATION
- 15284. PIPELINES
- 15285. TRANSIT AGENCY RESPONSES TO REVENUE SHORTFALLS
- Article 19. Categorical Exemptions
- 15300. CATEGORICAL EXEMPTIONS
- 15300.1. RELATION TO MINISTERIAL PROJECTS
- 15300.2. EXCEPTIONS
- 15300.3. REVISIONS TO LIST OF CATEGORICAL EXEMPTIONS
- 15300.4. APPLICATION BY PUBLIC AGENCIES
- 15301. EXISTING FACILITIES
- 15302. REPLACEMENT OR RECONSTRUCTION
- 15303. NEW CONSTRUCTION OR CONVERSION OF SMALL STRUCTURES
- 15304. MINOR ALTERATIONS TO LAND
- 15305. MINOR ALTERATIONS IN LAND USE LIMITATIONS
- 15306. INFORMATION COLLECTION
- 15307. ACTIONS BY REGULATORY AGENCIES FOR PROTECTION OF NATURA…
- 15308. ACTIONS BY REGULATORY AGENCIES FOR PROTECTION OF THE EN…
- 15309. INSPECTIONS
- 15310. LOANS
- 15311. ACCESSORY STRUCTURES
- 15312. SURPLUS GOVERNMENT PROPERTY SALES
- 15313. ACQUISITION OF LANDS FOR WILDLIFE CONSERVATION PURPOSES
- 15314. MINOR ADDITIONS TO SCHOOLS
- 15315. MINOR LAND DIVISIONS
- 15316. TRANSFER OF OWNERSHIP OF LAND IN ORDER TO CREATE PARKS
- 15317. OPEN SPACE CONTRACTS OR EASEMENTS
- 15318. DESIGNATION OF WILDERNESS AREAS
- 15319. ANNEXATIONS OF EXISTING FACILITIES AND LOTS FOR EXEMPT …
- 15320. CHANGES IN ORGANIZATION OF LOCAL AGENCIES
- 15321. ENFORCEMENT ACTIONS BY REGULATORY AGENCIES
- 15322. EDUCATIONAL OR TRAINING PROGRAMS INVOLVING NO PHYSICAL …
- 15323. NORMAL OPERATIONS OF FACILITIES FOR PUBLIC GATHERINGS
- 15324. REGULATIONS OF WORKING CONDITIONS
- 15325. TRANSFERS OF OWNERSHIP OF INTEREST IN LAND TO PRESERVE …
- 15326. ACQUISITION OF HOUSING FOR HOUSING ASSISTANCE PROGRAMS
- 15327. LEASING NEW FACILITIES
- 15328. SMALL HYDROELECTRIC PROJECTS AT EXISTING FACILITIES
- 15329. COGENERATION PROJECTS AT EXISTING FACILITIES
- 15330. MINOR ACTIONS TO PREVENT, MINIMIZE, STABILIZE, MITIGATE…
- 15331. HISTORICAL RESOURCE RESTORATION/REHABILITATION
- 15332. IN-FILL DEVELOPMENT PROJECTS
- 15333. SMALL HABITAT RESTORATION PROJECTS.
- Article 20. Definitions
- 15350. GENERAL
- 15351. APPLICANT
- 15352. APPROVAL
- 15353. CEQA
- 15354. CATEGORICAL EXEMPTION
- 15355. CUMULATIVE IMPACTS
- 15356. DECISION-MAKING BODY
- 15357. DISCRETIONARY PROJECT
- 15358. EFFECTS
- 15359. EMERGENCY
- 15360. ENVIRONMENT
- 15361. ENVIRONMENTAL DOCUMENTS
- 15362. EIR - ENVIRONMENTAL IMPACT REPORT
- 15363. EIS - ENVIRONMENTAL IMPACT STATEMENT
- 15364. FEASIBLE
- 15364.5. GREENHOUSE GAS
- 15365. INITIAL STUDY
- 15366. JURISDICTION BY LAW
- 15367. LEAD AGENCY
- 15368. LOCAL AGENCY
- 15369. MINISTERIAL
- 15369.5. MITIGATED NEGATIVE DECLARATION
- 15370. MITIGATION
- 15371. NEGATIVE DECLARATION
- 15372. NOTICE OF COMPLETION
- 15373. NOTICE OF DETERMINATION
- 15374. NOTICE OF EXEMPTION
- 15375. NOTICE OF PREPARATION
- 15376. PERSON
- 15377. PRIVATE PROJECT
- 15378. PROJECT
- 15379. PUBLIC AGENCY
- 15380. ENDANGERED, RARE OR THREATENED SPECIES
- 15381. RESPONSIBLE AGENCY
- 15382. SIGNIFICANT EFFECT ON THE ENVIRONMENT
- 15383. STATE AGENCY
- 15384. SUBSTANTIAL EVIDENCE
- 15385. TIERING
- 15386. TRUSTEE AGENCY
- 15387. URBANIZED AREA
- CEQA GUIDELINES APPENDICES
- APPENDIX A: CEQA PROCESS FLOW CHART
- APPENDIX B: STATUTORY AUTHORITY OF STATE DEPARTMENTS
- continued
- APPENDIX B FOOTNOTES
- APPENDIX C: NOTICE OF COMPLETION & ENVIRONMENTAL DOCUMENT TRAN…
- continued
- APPENDIX D: NOTICE OF DETERMINATION
- APPENDIX E: NOTICE OF EXEMPTION
- I. Introduction
- II. EIR Contents
- APPENDIX G: ENVIRONMENTAL CHECKLIST FORM
- ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED:
- DETERMINATION
- EVALUATION OF ENVIRONMENTAL IMPACTS
- APPENDIX H: ENVIRONMENTAL INFORMATION FORM
- APPENDIX I: NOTICE OF PREPARATION
- APPENDIX J: EXAMPLES OF TIERING EIRS
- APPENDIX K: CRITERIA FOR SHORTENED CLEARINGHOUSE REVIEW
- APPENDIX L: NOTICE OF COMPLETION OF DRAFT EIR
- I. Introduction
- II. Definitions
- Ill. Performance Standards Related to Project Design
- IV. Additional Performance Standards by Project Type
- A. Residential
- B. Commercial/Retail
- C. Office Building
- D. Transit
- E. Schools
- F. Small Walkable Community Projects
- G. Mixed-Use Projects
- APPENDIX N: INFILL ENVIRONMENTAL CHECKLIST FORM
- INDEX
- Schools
- www.califaep.org