23.18.010 Effective date.

Generally, the action to approve, conditionally approve, or deny a permit authorized by this title shall be effective on the eleventh (11th) day after the date of action, immediately following expiration of the ten (10) day appeal period. Legislative actions by the City Council (zoning amendment, General Plan amendment, specific plans, development agreements) become effective thirty (30) days from the date of final action and may not be appealed. In accordance with the California Civil Code and EGMC Section 23.12.030, Rules of interpretation, where the last of the specified number of days falls on a weekend or City holiday, the time limit of the appeal shall extend to the end of the next working day. Permit(s) shall not be issued until the effective date of required permit.

No application for a planning entitlement that has been denied shall be resubmitted within one (1) year from the date of final action, unless modified to address the basis for denial or when there is new evidence of proof of changed conditions found to be valid by the Planning Commission. [Ord. 8-2011 §9(A), eff. 6-24-2011]

23.18.020 Permit time limits.

A. Except as otherwise provided in this title or EGMC Title 22, any administrative and quasi-judicial permit or approval, including but not limited to conditional use permits (all types), minor deviations, variances, and design reviews (all types) not exercised within three (3) years from the date of final approval shall expire and become null and void.

B. Notwithstanding subsection (A) of this section, any administrative and quasi-judicial permit, including but not limited to conditional use permits (all types), minor deviations, variances, and design reviews (all types) approved but not yet fully exercised as of November 28, 2021, shall be valid for a period of four (4) years from the date of final approval, and shall thereafter expire and become null and void if not exercised within that four (4) year period. [Ord. 21-2020 §3, eff. 1-8-2021; Ord. 3-2018 §3 (Exh. C), eff. 4-13-2018; Ord. 26-2006 §3, eff. 8-11-2006]

23.18.030 Exercising permits.

The exercise of a permit occurs when the property owner has performed substantial work and incurred substantial liabilities in good faith reliance upon such permit(s). Such exercise of a permit constitutes the vested right to complete the work authorized by the permit. A permit may be otherwise exercised by a condition of the permit or corresponding legal agreement that specifies that other substantial efforts or expenditures constitute exercise of the permit. Finally, unless otherwise provided, permits that have not been exercised prior to a zoning amendment which makes the approved use or structure of the permit nonconforming shall automatically be deemed invalid on the effective date of the zoning amendment. [Ord. 26-2006 §3, eff. 8-11-2006]

23.18.040 Permit to run with land.

Unless otherwise conditioned, land use and development permits and approvals granted pursuant to the provisions of this chapter shall be transferable upon a change of ownership of the site, business, service, use or structures; provided, that the use and conditions of the original permit or approval are fully complied with, and the project is not modified or enlarged/expanded. [Ord. 26-2006 §3, eff. 8-112006]

23.18.050 Permit on site during construction.

A copy of all land use and development permits (including all corresponding stamped-approved plans) authorizing construction shall be kept on site at all times during construction. [Ord. 26-2006 §3, eff. 8- 11-2006]

23.18.060 Permit extension.

A. Any administrative or quasi-judicial permit or entitlement provided for in this title is eligible for an extension of time, provided the application for such extension is submitted at least sixty (60) days prior to the expiration of the original approval. The Zoning Administrator shall be the approval authority for such extensions. Upon a timely filing of an application for an extension of time, the permit or entitlement shall automatically be extended until the application for the extension is approved, conditionally approved, or denied. If, however, the permit or entitlement extension has not been brought forward for review by the Zoning Administrator within one hundred eighty (180) days of application for the extension, the permit or entitlement will be deemed expired. After the expiration of a permit or entitlement, the applicant will be required to reapply and pay the applicable fee(s) should they desire to move forward with their project. No grading permit, improvement plan, or building permit may be approved during the period between the expiration date of the original permit or entitlement and the approval of the extension of time. An extension of time may not be granted for more than thirty-six (36) months, but may be granted for a lesser time at the sole discretion of the Zoning Administrator. The permit or entitlement, as extended, may be conditioned to comply with any development standards that may have been enacted since the permit or entitlement was initially approved and any other conditions deemed appropriate by the approving authority. The extension may be granted only when the Zoning Administrator finds that the original permit or entitlement findings can be made and that there is no change of circumstance or that there has been diligent pursuit to exercise the permit that warrants such extension.

B. As provided in EGMC Section 22.16.100, any entitlement, development permit, or other approval that would expire pursuant to this title or EGMC Title 22, but that was approved concurrently with and pertains to any approved tentative subdivision or parcel map, the expiration date of which was automatically extended by the provisions of Sections 66452.11 and 66452.13 of the California Government Code, or by the provisions of any other similar section that may periodically be added to the California Government Code, or was extended by action of the Zoning Administrator, shall be extended for the same period as that provided by said section for the approved tentative subdivision or parcel map to which it pertains. [Ord. 13-2025 §3 (Exh. E), eff. 7-25-2025; Ord. 3-2018 §3 (Exh. C), eff. 4-13-2018; Ord. 262006 §3, eff. 8-11-2006] Home Previous Next

Home Previous Next

==> picture [9 x 9] intentionally omitted <==

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — Elk Grove Zoning Code
Elk Grove Zoning Code
  1. Chapter 23.02 — PURPOSE OF TITLE 23
  2. Chapter 23.04 — TITLE 23 APPLICABILITY
  3. Chapter 23.10 — IDENTIFICATION AND RESPONSIBILITIES OF
  4. Chapter 23.12 — INTERPRETATION AND ENFORCEMENT OF TITLE 23
  5. Chapter 23.14 — GENERAL APPLICATION PROCESSING PROCEDURES
  6. Chapter 23.16 — PERMIT REQUIREMENTS
  7. Chapter 23.17 — STREAMLINED HOUSING APPROVALS
  8. Chapter 23.18 — IMPLEMENTATION, TIME LIMITS AND EXTENSIONS
  9. Chapter 23.20 — MODIFICATION AND REVOCATION
  10. Chapter 23.24 — ESTABLISHMENT OF ZONING DISTRICTS
  11. Chapter 23.26 — USE CLASSIFICATION SYSTEM
  12. Chapter 23.27 — ALLOWED USES AND REQUIRED ENTITLEMENTS
  13. Chapter 23.28 — AGRICULTURAL ZONING DISTRICTS (Repealed)
  14. Chapter 23.29 — DEVELOPMENT STANDARDS BY ZONING DISTRICT
  15. Chapter 23.30 — DEVELOPMENT STANDARDS FOR QUALIFYING RESIDENTI…
  16. Chapter 23.32 — COMMERCIAL ZONING DISTRICTS (Repealed)
  17. Chapter 23.34 — OFFICE ZONING DISTRICTS (Repealed)
  18. Chapter 23.36 — INDUSTRIAL ZONING DISTRICTS (Repealed)
  19. Chapter 23.38 — OPEN SPACE ZONING DISTRICT (Repealed)
  20. Chapter 23.40 — SPECIAL PURPOSE ZONING DISTRICTS
  21. Chapter 23.42 — OVERLAY/COMBINING DISTRICTS
  22. Chapter 23.46 — ACCESSORY STRUCTURES
  23. Chapter 23.47 — BILLBOARD SIGNS
  24. Chapter 23.48 — BUILDING HEIGHT MEASUREMENTS AND EXCEPTIONS
  25. Chapter 23.50 — DENSITY BONUS AND OTHER DEVELOPER INCENTIVES
  26. Chapter 23.52 — FENCES AND WALLS
  27. Chapter 23.54 — LANDSCAPING
  28. Chapter 23.56 — LIGHTING
  29. Chapter 23.60 — PERFORMANCE STANDARDS
  30. Chapter 23.61 — PRIVATE PARTY SIGNS ON CITY PROPERTY
  31. Chapter 23.62 — SIGNS ON PRIVATE PROPERTY
  32. Chapter 23.63 — UNDERGROUNDING OF UTILITIES
  33. Chapter 23.64 — YARD MEASUREMENTS AND PROJECTIONS
  34. Chapter 23.68 — ACCESSORY USES
  35. Chapter 23.70 — ADULT-ORIENTED BUSINESSES
  36. Chapter 23.72 — AUTOMOBILE FUELING STATIONS
  37. Chapter 23.74 — BIG-BOX RETAIL DESIGN STANDARDS
  38. Chapter 23.76 — CONDOMINIUM CONVERSION
  39. Chapter 23.78 — DRIVE-IN AND DRIVE-THROUGH FACILITY
  40. Chapter 23.80 — EMERGENCY SHELTERS
  41. Chapter 23.82 — HOME OCCUPATIONS
  42. Chapter 23.83 — INDOOR PERSONAL MARIJUANA CULTIVATION
  43. Chapter 23.84 — NONCONFORMING USES, BUILDINGS, AND STRUCTURES
  44. Chapter 23.85 — MOBILE FOOD VENDORS
  45. Chapter 23.86 — OUTDOOR SALES, DISPLAY, STORAGE, AND SEATING
  46. Chapter 23.88 — CARE FACILITIES
  47. Chapter 23.90 — ACCESSORY DWELLING UNITS
  48. Chapter 23.92 — TEMPORARY USES
  49. Chapter 23.93 — URBAN CROP PRODUCTION
  50. Chapter 23.94 — WIRELESS COMMUNICATIONS FACILITIES
  51. Chapter 23.98 — DEFINITIONS (Repealed)
  52. Chapter 23.100 — GENERAL DEFINITIONS

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.