Sec. 25-61. - Extension of improvement agreements.

Sonoma County Planning Code · 2026-07 edition · updated 2026-07-25 · Sonoma County

The completion date for any improvements to be constructed under an improvement agreement may be extended by the advisory agency upon written request by the subdivider and the submittal of evidence to justify such extension. The request shall be made not less than thirty (30) days prior to the expiration of the improvement agreement. In consideration of the extension, the following will be required:

(a)

Revision of the improvement plan to provide the current design and construction standards required by the responsible department;

(b)

Revised improvement construction estimate to reflect current improvement costs as approved by the responsible department;

(c)

Increase of improvement securities in accordance with revised construction estimates;

(d)

Increase in any inspection fees to reflect current fees.

The advisory agency may impose additional requirements as it may deem necessary or convenient as a condition to approving any time extensions for the completion of improvements.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — Sonoma County Planning Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.