Solar panels and EV chargers in Anaheim

Anaheim's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Anaheim Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Anaheim's code says

Anaheim code What Anaheim's code adds
EV charger permit
  • No permit under this chapter, unless changes materially alter the station's size, type or components.
    Applies: Applies to charging stations set up or permitted before this chapter took effect.
    § 15.05.040 · code text
    Notwithstanding the foregoing, any Electric Vehicle Charging Station established or permitted prior to the effective date of this Chapter shall not require a permit issued under Section .040 of this Chapter unless physical modifications or alterations are undertaken that materially change the size, type, or components of the Electric Vehicle Charging Station.
  • The Building Official issues the permit if all requirements are met with no specific, adverse public health or safety impact.
    § 15.05.060 · code text
    The Building Official will review a completed application and determine whether to issue a Charging Station Permit. The Building Official will issue the Charging Station Permit; provided, the Building Official determines proposed installation meets all of the requirements set forth in subsection .030 of Section 15.05.040 and will not have a Specific, Adverse Impact upon the public health and safety.
Solar permit process
  • Expedited administrative approval and all permits after a complete checklist application. Apply in person, by mail or electronically, with fees.
    Applies: Applies to small home rooftop solar energy systems eligible for expedited review.
    § 15.04.060 · code text
    Upon confirmation by the Building Official of the application and supporting documentation being complete and meeting the requirements of the checklist, the Building Official shall administratively approve the application and issue all required permits or authorizations.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Anaheim?

Anaheim's code: Expedited administrative approval and all permits after a complete checklist application. Apply in person, by mail or electronically, with fees. (Applies to small home rooftop solar energy systems eligible for expedited review.) (§ 15.04.060); No permit under this chapter, unless changes materially alter the station's size, type or components. (Applies to charging stations set up or permitted before this chapter took effect.) (§ 15.05.040).

General information, not legal advice.