Solar panels and EV chargers in Galt

Galt's own rules on solar panels and EV chargers, with the code text for every value.

Each rule below links to the section of the Galt Municipal Code it was read from, with the code text one click away (checked October 2026). General information, not legal advice.

What Galt's code says

Galt code What Galt's code adds
EV charger permit
  • The Building Official approves and issues all permits when the application meets the City's adopted checklist.
    Applies: Applies to electric vehicle charging stations; the application must also meet all applicable laws.
    § 15.07.060 · code text
    Upon confirmation by the Building Official that the permit application and supporting documents meet the requirements of the City's adopted checklist, and is consistent with all applicable laws, the Building Official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits.
Solar permit process
  • Administrative, nondiscretionary review; a permit issues for a complete application meeting the checklist and standard plan; only 1 inspection.
    Applies: Applies to small rooftop home solar systems eligible for fast review.
    § 15.06.060 · code text
    Only one (1) inspection shall be required and performed by the Building Department for small residential rooftop solar energy systems eligible for expedited review.
Review time
  • Same day.
    Applies: Applies to complete over-the-counter applications for small rooftop home solar that meet the checklist and standard plan.
    § 15.06.060 · code text
    The Building Division shall issue a building permit or other nondiscretionary permit (the same day for over-the-counter applications or within one (1) to three (3) business days for electronic applications) on receipt of a complete application that meets the requirements of the approved checklist and standard plan.
  • Within 1 to 3 business days.
    Applies: Applies to complete electronic applications for small rooftop home solar that meet the checklist and standard plan.
    § 15.06.060 · code text
    The Building Division shall issue a building permit or other nondiscretionary permit (the same day for over-the-counter applications or within one (1) to three (3) business days for electronic applications) on receipt of a complete application that meets the requirements of the approved checklist and standard plan.
  • Inspection scheduled within 2 business days of a request, with a 2-hour inspection window.
    Applies: Applies to small rooftop home solar systems.
    § 15.06.060 · code text
    An inspection will be scheduled within two (2) business days of a request and provide a two (2) hour inspection window.

Who this affects

HomeownersContractorsDesigners

Frequently asked questions

Do I need a permit for solar panels or an EV charger in Galt?

Galt's code: Administrative, nondiscretionary review; a permit issues for a complete application meeting the checklist and standard plan; only 1 inspection. (Applies to small rooftop home solar systems eligible for fast review.) (§ 15.06.060); The Building Official approves and issues all permits when the application meets the City's adopted checklist. (Applies to electric vehicle charging stations; the application must also meet all applicable laws.) (§ 15.07.060).

General information, not legal advice.