Sacramento MIP zoning: height, setbacks and lot size

In Sacramento's MIP zone, buildings can be up to 40 feet tall and the front setback is 25 feet (Sacramento code, read October 2026).

Key points

  • Maximum building height: 40 feet
  • Minimum front setback: 25 feet
  • Minimum side setback: No minimum (Unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below)
  • Minimum rear setback: No minimum (Unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below)

MIP (Manufacturing-Industrial Park Zone) is a zoning district in Sacramento. Every value below was read from the Sacramento Municipal Code and links to its section (read October 2026). State laws such as the ADU and SB 9 rules can allow more on a residential lot. General information, not legal advice — read the code text and check with the city before you build.

Development standards in MIP

The general rule for a typical lot in this zone. Zoning tables often attach notes, such as rules for corner lots, lots next to a residential zone, or new subdivisions only. Open “code text” under a value to see the table cell or sentence it was read from.

Maximum building height
40 feet
§ 17.220.520 · code text
The maximum height is 40 feet.
Minimum front setback
25 feet
§ 17.220.530 · code text
The minimum front yard setback is 25 feet.
Minimum side setback
No minimum
Applies: Unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below
§ 17.220.530 · code text
No minimum side yard setback is required unless the side yard abuts the side of an R- or OB-zoned lot, in which case a minimum setback of 150 feet or 10 feet landscaped setback, respectively, is required.
Minimum rear setback
No minimum
Applies: Unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below
§ 17.220.530 · code text
No minimum rear yard setback yard setback is required unless the rear yard abuts the side of an R- or OB-zoned lot, in which case a minimum setback of 150 feet or 25 feet, respectively, is required.

When a different number applies

The code sets other values for particular lots, buildings or locations in MIP:

  • Minimum side setback: 150 feet — Side yard abuts the side of an R-zoned lot § 17.220.530
  • Minimum side setback: 10 feet — Side yard abuts the side of an OB-zoned lot; landscaped setback § 17.220.530
  • Minimum rear setback: 150 feet — Rear yard abuts the side of an R-zoned lot § 17.220.530
  • Minimum rear setback: 25 feet — Rear yard abuts the side of an OB-zoned lot § 17.220.530

Not on this page

We did not find a general stories, lot size, lot coverage, FAR, density limit for MIP in the zoning tables we read. The code may still set one elsewhere — check the Sacramento Municipal Code.

Other Sacramento zoning districts

Who this affects

HomeownersArchitects and designersDevelopersReal estate agents

Frequently asked questions

What is the maximum building height in Sacramento's MIP zone?

40 feet — Sacramento Municipal Code § 17.220.520.

What is the minimum front setback in Sacramento's MIP zone?

25 feet — Sacramento Municipal Code § 17.220.530.

What is the minimum side setback in Sacramento's MIP zone?

No minimum (unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below) — Sacramento Municipal Code § 17.220.530.

What is the minimum rear setback in Sacramento's MIP zone?

No minimum (unless the yard abuts an R- or OB-zoned lot; larger setbacks apply, see below) — Sacramento Municipal Code § 17.220.530.

General information, not legal advice.

Ask about a Sacramento property in MIP

Ask GoCodebook what you can build at a specific address and get an answer that cites the section.

Ask your question

More on Sacramento