19-9 Filing Procedure Generally; Filing Fee

  1. After receipt of the report of the city council approving or conditionally approving the tentative map of a subdivision, the subdivider may, within one year from the date of such approval, proceed to prepare and file a final map as provided in this article. If such final map is not submitted within one year from the date of the approval of the tentative map, such map shall be considered abandoned.
  2. For the purposes of filing a final map, the subdivider shall submit to the city manager an original final map tracing and three dark line prints thereof. One copy of such dark line print shall be filed permanently with the city manager. One copy shall be transmitted to the city manager for checking and report to the city planning commission. One copy shall be returned to the subdivider after showing thereon corrections, if any, or a statement by the city manager that the map is correct. When the map is found to be correct, the final map tracing shall be certified by the city manager and the city clerk and returned to the subdivider for recording.
  3. After the final map has been recorded in the county recorder’s office, one cloth print and one paper print of such map shall be furnished to the city manager.
  4. When requested, traverse sheets and work sheets showing the closure of the exterior boundaries and of each irregular block and lot shall be approved.
  5. At the time of the submission to the secretary of the planning commission of a final map for examination and certification, the subdivider shall pay to the city a fee in the sum of two hundred dollars plus the estimated costs incurred by the city engineer in checking the final map. If overpayment is made to the city, the subdivider shall be refunded such overpayment. If underpayment is made, the subdivider shall be billed the difference, which said bill shall be due and payable within thirty days upon receipt of such bill. (Ord. No. 251 N.S., § 97.15; Ord. No. 297 N.S., § 10; Ord. No. 152-AC (part); Ord. No. 223-AC (part); Ord. No. 361-AC.)
Exceptions & meaning →

19-10 Size; Form

  1. The final map of a subdivision shall be clearly and legibly delineated upon tracing cloth of good quality. All lines, letters, figures, certificates, acknowledgements and signatures shall be made in black, waterproof India ink; except, that affidavits and certificates may be legibly stamped or printed upon the map with black opaque ink.
  2. The size of each sheet shall be eighteen by twenty-six inches.
  3. A marginal line shall be drawn completely around each sheet, leaving an entirely blank margin of one inch.
  4. The scale of the map shall be large enough to show all details clearly, and enough sheets shall be used to accomplish this end.
  5. Each sheet shall be numbered, the relation of one sheet to another clearly shown and the number of sheets used shall be set forth on each sheet.
  6. The tract number, scale and north point shall be shown on each sheet of the final map. (Ord. No. 297 N.S., § 7.)
Exceptions & meaning →

19-11 Title Sheet

  1. Below the title on a final map of a subdivision shall be a subtitle consisting of a general description of all the property being subdivided, by reference to subdivisions or to sectional surveying.
  2. Reference to tracts any subdivisions shall be spelled out and worded identically with the original records, with complete reference to the proper book and page of the record.
  3. The title sheet shall show, in addition, the basis of bearings.
  4. Maps filed for the purpose of reverting subdivided land to acreage shall be conspicuously marked under the title “The-Purpose of This Map is a Revision to Acreage.” (Ord. No. 297 N.S., § 8.)
Exceptions & meaning →

19-12 Information To Be Shown--Generally

In addition to the information required on the final map by other provisions of this chapter, and the Subdivision Map Act,1 the following information should be required:

  1. Title, number of tract, date, north point and scale.
  2. Description of land included.
  3. Location and names, without abbreviations, of all the following:
  4. Proposed streets and alleys.
  5. Proposed public areas and easements.
  6. Adjoining streets.
  7. Each lot shall be numbered, each block may be lettered or numbered and each lot shall be shown entirely on one sheet.
  8. Any final map presented to the city for acceptance of easements and recordation shall be accompanied by an additional copy on which is delineated all existing and proposed structures and utilities within the subdivision.
  9. At the time the subdivider presents the final map to the city council there shall be presented certificates executed respectively by the various public utility companies authorized to serve in the area of the subdivision, certifying that satisfactory provisions have been made with each of the public utility companies as to location of their facilities; and that easements where required by such companies have been executed and delivered to the certifying companies for recording. Easements for public utility companies shall be designated on the final map as “Easements for Public Utilities”.
  10. Any other reasonable or pertinent information required by the city council. (Ord. No. 297 N.S., § 5.)

1 See. B. & P.C., § 11000 et seq.

Exceptions & meaning →

19-13 Same--Street Names

Each street shown on the final map of a subdivision which is to be dedicated and which is a continuation, or in line of prolongation, of any existing dedicated streets shall be given the same name as such existing street. The proposed name of each other street shown on such map shall be submitted to the city clerk for his approval; no name may be approved which is a duplicate of or so nearly the same as to cause confusion with the name of any existing street located in the city or in the nearby vicinity thereof. (Ord. No. 251 N.S., § 97.18.)

Exceptions & meaning →

19-14 Same--Rights-Of-Way

There shall be shown upon the final map of a subdivision the center line of each street, the total width thereof, the width of that portion to be dedicated, and in the case of any existing streets, the width of each street on each side of the center of the line thereof. The width of each railroad right of way, flood control or drainage channel, and of each other easement appearing thereon shall be shown on such final map. (Ord. No. 251 N.S., § 97.19.)

Exceptions & meaning →

19-15 Same--Easements

  1. Upon the final map of a subdivision shall be shown the center line or side lines of each easements to which the lots in such subdivision are subject. In the event that such easement is not definitely located of record, a statement showing the existence of such easement shall be placed on the title sheet of such map.
  2. Each statement for any storm drain, sewer or for light and air shall be designated on the final map by fine dotted lines.
  3. Distances and bearings on the side lines of lots which are cut by any easement shall be arrowed or so shown that the final map will indicate clearly the actual length of each lot line.
  4. The width of each easement or the lengths and bearings of the lines thereof and sufficient ties thereto to definitely locate such easements with respect to the subdivision shall be shown on such final map.
  5. Each such easement shall be clearly labeled and identified and, if already of record, its record reference shall be shown thereon; if not of record a statement of such easement shall be placed on the title sheet of such final map.
  6. If any easement is being dedicated by such final map it shall be properly set out in the owner’s certificate and dedication on such map.
  7. All notes or figures pertaining to each such easement shall be smaller and lighter than those relating to the subdivision itself. (Ord. No. 251 N.S., § 97.20 to 97.26.)
Exceptions & meaning →

19-16 Same--City Boundary Line

Upon the final map of a subdivision shall be shown each city boundary line crossing or adjoining such subdivision and such line shall be clearly designated and tied in. (Ord. No. 251 N.S., § 97.27.)

Exceptions & meaning →

19-17 Required Surveying Data And Procedure

  1. Each final map of a subdivision shall have indicated thereon the following:
  2. Radius, tangent arc and central angle of curves.
  3. Suitable primary survey control points as follows:
  4. Section corners.
  5. Monuments (existing outside of the subdivision).
  6. Location of all permanent monuments within the subdivision.
  7. Ties to and identification of adjacent subdivisions.
  8. Ties to any city or county boundary lines involved.
  9. Required certificates.
  10. The following surveying data for lots shall be shown on the final map:
  11. Sufficient data shall be shown to determine readily the bearing and length of each line.
  12. Dimensions shall be the net dimensions.
  13. No ditto marks shall be used.
  14. Lots containing one acre or more shall show net acreage to the nearest hundredth.
  15. Lots requiring both a septic system and well shall be a minimum of one gross acre.
  16. The final map shall show the center lines of all streets; length, tangents, radii and central angles or radial bearings of all curves; the total width of each street; the width of the portion being dedicated, the width of existing dedication and the width of each side of the center line; and the width of rights-of-way of railroads, flood control or drainage channels and any other easements existing or being dedicated by the map. A traverse of the boundaries of the subdivision and all lots and block shall close.
  17. In making the survey for the subdivision, the surveyor shall set sufficient permanent monuments so that the survey or any part thereof may be readily retracted. Such monuments shall generally be placed at angle points on the exterior boundary lines of the tract, and at intersections of center lines of streets and at the beginning of curves and at the end of curves on center lines. Such monuments may be placed on offset lines. Stakes set at lot corner will not be considered permanent. The character, type and positions of all monuments shall be noted on the map.
  18. For each center line intersection monument set, the engineer or surveyor under whose supervision the survey has been made shall furnish to the city manager a set of notes showing clearly the ties between such monument and a sufficient number (normally four) of durable, distinctive reference points or monuments. Such reference points or monuments may be leads and tacks in sidewalks, or two-inch iron pipe set back of the curb line and below the surface of the ground or such substitute therefor as appears to be not more likely to be disturbed.

Such set of notes shall be of such quality, form and completeness and shall be on paper of such quality and size as may be necessary to the standardized office records of the city manager’s office. 6. Whenever the city manager has established the center line of a street or alley, such data shall be considered in making the survey and in preparing the final map, and all monuments found shall be indicated and proper reference made to field books or maps of public record, relating to the monument. If the points have been reset by ties, that fact shall be stated. 7. The final map shall show city boundaries crossing or adjoining the subdivision clearly designated and tied in. (Ord. No. 297 N.S., §§ 6, 9.)

Exceptions & meaning →

19-18 Approval Of City Manager

After receiving copies of the final map of a subdivision, the city manager shall examine or have examined the map as to sufficiency of affidavits and acknowledgments, correctness of surveying data, mathematical data and computations and such other matters as required, checking to insure compliance with the provisions of the Subdivision Map Act and of this chapter. If the final map is found to be in correct form and the matters shown thereon are sufficient, the city manager shall endorse his approval thereon and transmit it to the city council. (Ord. No. 297 N.S., § 11.)

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Needles Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.