Chapter 6C — ELECTRIC RATES›Article 6C — II CONDITIONS GOVERNING THE EXTENSION OF ELECTRIC DISTRIBUTION AND SERVICES
Needles Municipal Code § 8.1 General policy
Needles Municipal Code · 2026-10 edition · updated 2026-10-21 · Needles
Cite as: Needles Municipal Code § 8.1 · Text as of 2026-10-21
8.1.1 Extension shall be for a new permanent Customer or group of new permanent Customers.¶
A Customer shall be considered permanent when:
(a) Service will be rendered to Customer for a period greater than twelve (12) months;
(b) Removal of the electric facilities is not being planned after a specific period or upon completion of the project;
(c) Customer has completed an application for service;
(d) The meter will be installed within thirty (30) days after completion of the extension.
8.1.2 The total extension is determined to be economically feasible for City, as defined in section 8.2.¶
8.1.3 Customer pays total extension costs in advance of scheduling construction,…¶
Continue researching
Needles sources →Needles local, state and federal sources. Edit the document title or filters, then run your search.
Get a plain-English answer with a citation back to this text.
Ask AI about this code