1107.2 Methods of Testing Storm Drainage Systems — 2025 California Plumbing Code
California Plumbing Code (Title 24, Part 5) · 2025 edition · updated 2026-10-19 · California
CBSC: official editions, supplements and errata
Italicized text is a California amendment to the model code, as printed in the official publication.
Cite as: 2025 California Plumbing Code (Title 24, Part 5) § 1107.2 · Effective January 1, 2026 · Official source: Building Standards Commission
Except for outside leaders and perforated or open-jointed drain tile, the piping of storm drain systems shall be tested upon completion of the rough piping installation by water or air, except that plastic pipe shall not be tested with air, and proved tight. The Authority Having Jurisdiction shall be permitted to require the removal of cleanout plugs to ascertain whether the pressure has reached parts of the system. One of the following test methods shall be used in accordance with Section 1107.2.1 through Section 1107.2.3. 1107.2.1 Water Test. After piping has been installed, the water test shall be applied to the drainage system, either to the entire system or sections. Where the test is applied to the entire system, all openings in the piping shall be tightly closed except for the highest opening, and the system shall be filled with water to the point of overflow. Where the system is tested in sections, each opening shall be tightly plugged except for the highest opening of the section under test, and each section shall be filled with water, but no section shall be tested with less than a 10 foot (3048 mm) head of water. In testing successive sections, not less than the upper 10 feet (3048 mm) of the next preceding section shall be tested so that no joint of pipe in the building except the uppermost 10 feet (3048 mm) of a roof drainage system, which shall be filled with water to the flood level of the uppermost roof drain, shall have been submitted to a test of less than 10 foot (3048 mm) head of water. The water shall be kept in the system or the portion of the test for not less than 15 minutes before inspection starts; the system shall then be tight. 1107.2.2 Air Test. The air test shall be made by attaching an air compressor testing apparatus to a suitable opening after closing other inlets and outlets to the system, forcing air into the system until there is a uniform gauge pressure of 5 pounds-force per square inch (psi) (34 kPa) or sufficient pressure to balance a column of mercury 10 inches (34 kPa) in height. This pressure shall be held without the introduction of additional air for not
less than 15 minutes.
1107.2.3 Exceptions. Where circumstances exist that make air and water tests described in Section 1107.2.1 and Section 1107.2.2 impractical, see Section 105.3.
| TABLE 1103.2 SIZING OF HORIZONTAL RAINWATER PIPING1, 2 | |||||||
|---|---|---|---|---|---|---|---|
| SIZE OF PIPE | FLOW (1⁄8 inch per foot slope) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
| inches | gpm | 1 (in/h) | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 34 | 3288 | 1644 | 1096 | 822 | 657 | 548 |
| 4 | 78 | 7520 | 3760 | 2506 | 1880 | 1504 | 1253 |
| 5 | 139 | 13 360 | 6680 | 4453 | 3340 | 2672 | 2227 |
| 6 | 222 | 21 400 | 10 700 | 7133 | 5350 | 4280 | 3566 |
| 8 | 478 | 46 000 | 23 000 | 15 330 | 11 500 | 9200 | 7670 |
| 10 | 860 | 82 800 | 41 400 | 27 600 | 20 700 | 16 580 | 13 800 |
| 12 | 1384 | 133 200 | 66 600 | 44 400 | 33 300 | 26 650 | 22 200 |
| 15 | 2473 | 238 000 | 119 000 | 79 333 | 59 500 | 47 600 | 39 650 |
| SIZE OF PIPE | FLOW (1⁄4 inch per foot slope) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
|||||
|---|---|---|---|---|---|---|---|
| inches | gpm | 1 (in/h) | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 48 | 4640 | 2320 | 1546 | 1160 | 928 | 773 |
| 4 | 110 | 10 600 | 5300 | 3533 | 2650 | 2120 | 1766 |
| 5 | 196 | 18 880 | 9440 | 6293 | 4720 | 3776 | 3146 |
| 6 | 314 | 30 200 | 15 100 | 10 066 | 7550 | 6040 | 5033 |
| 8 | 677 | 65 200 | 32 600 | 21 733 | 16 300 | 13 040 | 10 866 |
| 10 | 1214 | 116 800 | 58 400 | 38 950 | 29 200 | 23 350 | 19 450 |
| 12 | 1953 | 188 000 | 94 000 | 62 600 | 47 000 | 37 600 | 31 350 |
| 15 | 3491 | 336 000 | 168 000 | 112 000 | 84 000 | 67 250 | 56 000 |
| SIZE OF PIPE | FLOW (1⁄2 inch per foot slope) |
MAXIMUM ALLOWABLE HORIZONTAL PROJECTED ROOF AREAS AT VARIOUS RAINFALL RATES (square feet) |
|||||
|---|---|---|---|---|---|---|---|
| inches | gpm | 1 (in/h) | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 68 | 6576 | 3288 | 2192 | 1644 | 1310 | 1096 |
| 4 | 156 | 15 040 | 7520 | 5010 | 3760 | 3010 | 2500 |
| 5 | 278 | 26 720 | 13 360 | 8900 | 6680 | 5320 | 4450 |
| 6 | 445 | 42 800 | 21 400 | 14 267 | 10 700 | 8580 | 7140 |
| 8 | 956 | 92 000 | 46 000 | 30 650 | 23 000 | 18 400 | 15 320 |
| 10 | 1721 | 165 600 | 82 800 | 55 200 | 41 400 | 33 150 | 27 600 |
| 12 | 2768 | 266 400 | 133 200 | 88 800 | 66 600 | 53 200 | 44 400 |
| 15 | 4946 | 476 000 | 238 000 | 158 700 | 119 000 | 95 200 | 79 300 |
For SI units: 1 inch = 25 mm, 1 gallon per minute = 0.06 L/s, 1/8 inch per foot = 10.4 mm/m, 1 inch per hour = 25.4 mm/h, 1 square foot = 0.0929 m [2]
Notes: 1 The sizing data for horizontal piping are based on the pipes flowing full. 2 For rainfall rates other than those listed, determine the allowable roof area by dividing the area given in the 1 inch per hour (25.4 mm/h) column by the desired rainfall rate.
| TABLE 1103.3 SIZE OF GUTTERS | |||||
|---|---|---|---|---|---|
| DIAMETER OF GUTTER (1⁄16inch per foot slope) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
| inches | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 340 | 226 | 170 | 136 | 113 |
| 4 | 720 | 480 | 360 | 288 | 240 |
| 5 | 1250 | 834 | 625 | 500 | 416 |
| 6 | 1920 | 1280 | 960 | 768 | 640 |
| 7 | 2760 | 1840 | 1380 | 1100 | 918 |
| 8 | 3980 | 2655 | 1990 | 1590 | 1325 |
| 10 | 7200 | 4800 | 3600 | 2880 | 2400 |
| DIAMETER OF GUTTER (1⁄8 inch per foot slope) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
||||
|---|---|---|---|---|---|
| inches | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 480 | 320 | 240 | 192 | 160 |
| 4 | 1020 | 681 | 510 | 408 | 340 |
| 5 | 1760 | 1172 | 880 | 704 | 587 |
| 6 | 2720 | 1815 | 1360 | 1085 | 905 |
| 7 | 3900 | 2600 | 1950 | 1560 | 1300 |
| 8 | 5600 | 3740 | 2800 | 2240 | 1870 |
| 10 | 10 200 | 6800 | 5100 | 4080 | 3400 |
| DIAMETER OF GUTTER (1⁄4 inch per foot slope) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
||||
|---|---|---|---|---|---|
| inches | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 680 | 454 | 340 | 272 | 226 |
| 4 | 1440 | 960 | 720 | 576 | 480 |
| 5 | 2500 | 1668 | 1250 | 1000 | 834 |
| 6 | 3840 | 2560 | 1920 | 1536 | 1280 |
| 7 | 5520 | 3680 | 2760 | 2205 | 1840 |
| 8 | 7960 | 5310 | 3980 | 3180 | 2655 |
| 10 | 14 400 | 9600 | 7200 | 5750 | 4800 |
| DIAMETER OF GUTTER (1⁄2 inch per foot slope) |
MAXIMUM RAINFALL RATES BASED ON ROOF AREA (square feet) |
||||
|---|---|---|---|---|---|
| inches | 2 (in/h) | 3 (in/h) | 4 (in/h) | 5 (in/h) | 6 (in/h) |
| 3 | 960 | 640 | 480 | 384 | 320 |
| 4 | 2040 | 1360 | 1020 | 816 | 680 |
| 5 | 3540 | 2360 | 1770 | 1415 | 1180 |
| 6 | 5540 | 3695 | 2770 | 2220 | 1850 |
| 7 | 7800 | 5200 | 3900 | 3120 | 2600 |
| 8 | 11 200 | 7460 | 5600 | 4480 | 3730 |
| 10 | 20 000 | 13 330 | 10 000 | 8000 | 6660 |
For SI units: 1 inch = 25 mm, 1/16 inch per foot = 5.2 mm/m, 1 inch per hour = 25.4 mm/h, 1 square foot = 0.0929 m [2]
Explained in plain English
Guides that cite this section.
Continue researching
Related topics
State and federal sources. Edit the document title or filters, then run your search.
Get a plain-English answer with a citation back to this text.
Ask AI about this code