Chapter 86.06 — TIME LIMITATIONS
San Bernardino County Zoning Code · 2026-06 edition · updated 2026-07-25 · San Bernardino County
§ 86.06.010 Purpose. ¶
This Chapter provides requirements for the implementation or “exercising” of the permits and authorizations required by this Development Code, including time limits and procedures for granting extensions of time. (Ord. 4011, passed - -2007)
§ 86.06.020 Effective Date of Permits. ¶
(a) Effective Date for Planning Permits and Other Approvals. Except in the case of an amendment (Chapter 86.12) or development agreement (Chapter 86.13), final action on any planning approval (e.g., appeal, permit, Variance, or other entitlement) shall become effective on the eleventh day following the date of application approval, where no appeal of the approval has been filed in compliance with Chapter 86.08 (Appeals).
(b) When the Tenth Day Is Not a County Business Day. When the tenth day is not a County business day, the decision shall instead become effective on the second consecutive County business day following the tenth day. (Ord. 4011, passed - -2007; Am. Ord. 4085, passed - -2009)
§ 86.06.030 Applications Deemed Approved. ¶
A planning permit application for a parcel that is deemed approved by operation of law in compliance with Government Code § 65956 shall be subject to all applicable provisions of this Development Code, which shall be satisfied by the applicant before a Building Permit is issued or a land use not requiring a Building Permit is established.
(Ord. 4011, passed - -2007)
§ 86.06.040 Permits to Run with the Land. ¶
A Conditional Use Permit, Minor Use Permit, Site Plan Permit, Major or Minor Variance, Planned Development Permit, or Special Use Permit approval that is granted in compliance with Division 5 (Permit Application and Review Procedures) shall be deemed to run with the land through any change of ownership of the subject site, from the effective date of the permit, except in any case where a permit expires and becomes void in compliance with this Chapter. All applicable conditions of approval shall continue to apply after a change in property ownership. (Ord. 4011, passed - -2007; Am. Ord. 4085, passed - -2009)
§ 86.06.050 Performance Guarantees. ¶
(a) Deposit of Security.
(1) As a condition of approval of a Conditional Use Permit, Minor Use Permit, Major or Minor Variance, Planned Development Permit, Special Use Permit, Temporary Special Event Permit, Temporary Use Permit, or upon a finding that the County’s health, safety, and welfare warrant, the review authority may require the execution of a covenant to deposit security, and the deposit of security in a reasonable amount to ensure the faithful performance of one or more of the conditions of approval of the Conditional Use Permit, Minor Use Permit, Major or Minor Variance, Planned
Development Permit, Special Use Permit, Temporary Special Event Permit, or Temporary Use Permit in the event that the obligor fails to perform.
(2) The applicant/owner may elect to provide adequate security for the faithful performance of a condition(s) of approval imposed as part of the approval process if the Director determines that the condition(s) may be implemented at a later specified date (e.g., inability to install required landscaping due to poor weather conditions).
(3) The security shall, as required by law or otherwise at the option of the County, be in the form of cash, a certified or cashier’s check, letter of credit, a performance bond or other form of surety executed by the applicant and a corporate surety authorized to do business in California and approved by the County.
(4) The security shall remain in effect until all of the secured conditions have been performed to the satisfaction of the Director.
(5) Any security required in compliance with this Section shall be payable to the County.
(b) Release of Security. Upon satisfactory compliance with all applicable provisions of this Section, the security deposit shall be released.
(c) Failure to Comply.
(1) Upon failure to perform any secured condition, the County may perform the condition, or cause it to be done, and may collect from the obligor, and surety in case of a bond, all costs incurred, including administrative, engineering, legal, and inspection costs.
(2) Any unused portion of the security shall be refunded to the obligor after deduction of the cost of the work.
(3) To the extent that the Director can demonstrate that the obligor willfully breached an obligation in a manner that the obligor knew, or should have known, would create irreparable harm to the County, the entire amount of the bond or deposit may be withheld.
(4) The Director’s determination may be appealed to the Board by the obligor by filing an appeal with the Clerk of the Board within ten days after the decision to withhold the bond, in compliance with Chapter 86.08 (Appeals). (Ord. 4011, passed - -2007)
§ 86.06.060 Time Limits and Extensions. ¶
(a) Time Limits.
(1) Specified Item Shall Be Exercised Within 36 Months. Unless a condition of approval or other provision of this Development Code establishes a different time limit, a Conditional Use Permit, Minor Use Permit, Major or Minor Variance, Planned Development Permit, Tentative Parcel Map or Tentative Tract Map not exercised within 36 months of the actual date of the decision granting the permit or authorization shall expire and become void, except where an extension of time is approved in compliance with Subdivision (b) (Extensions of Time), below.
(2) Specified Item Shall Be Exercised Within 12 Months. Unless another provision of this Development Code establishes a different time limit, a Site Plan Permit, Special Use Permit, or Temporary Use Permit not exercised within 12 months of the actual date of the decision granting the permit or authorization shall expire and become void, except where an extension of time is approved in compliance with Subdivision (b) (Extensions of Time), below.
(3) Definition of “Exercised.” The permit or authorization shall not be deemed “exercised” until the permittee has commenced actual construction or alteration under a valid Building Permit, or has substantially commenced the approved activity or allowed use on the site in compliance with the conditions of approval, in cases where a Building Permit is not required.
(4) Run with the Land. After it has been exercised, a planning permit or authorization shall remain valid and run with the land in compliance with § 86.06.040 (Permits to Run with the Land), as long as a Building Permit is active for the project, and after a final building inspection or Certificate of Occupancy has been granted.
(5) Phased Projects.
(A) Projects Other than Planned Development Permits. If a project (other than a Planned Development Permit) is to be developed in approved phases, each subsequent phase shall be exercised within 36 months from the date that the previous phase was exercised, unless otherwise specified in the permit or authorization, or the permit or authorization shall expire and become void, except where an extension of time is approved in compliance with Subdivision (b). (Extensions of time), below. If the project also involves the approval of a Tentative Map, the phasing shall be consistent with the Tentative Map and the permit or authorization shall be exercised before the expiration of the Tentative Map, or the permit or authorization shall expire and become void
and become void, except where an extension of time is approved in compliance with Subdivision (b). (Extensions of time), below. If the project also involves the approval of a Tentative Map, the phasing shall be consistent with the Tentative Map and the permit or authorization shall be exercised before the expiration of the Tentative Map, or the permit or authorization shall expire and become void
(B) Planned Development Permits. Notwithstanding the above provisions of this Section, a conditionally approved Planned Development Permit for a phased project shall be subject to a time limitation not to exceed that specified by the condition of approval for the Development Plan approval. The applicant, however, shall either record a tract map or obtain Building Permits for at least one phase of the project within five years of the Development Plan conditional approval and, as applicable, within each succeeding five-year period. Each five-year period shall begin with the last County approved action that was accomplished (e.g., recordation of a tract map, obtain a Building Permit).
(6) First Amendment Protected Businesses.
(A) Time Limits for First Amendment Protected Businesses. The Director shall accept as complete, or disapprove as incomplete, the application for a Conditional Use Permit for a business protected by the First Amendment within 30 days from the date on which an application is submitted to the Director. The Director shall approve or disapprove the completed Conditional Use Permit application within 90 days of its acceptance as complete by the Director. The time limit established by this Section may be extended once for a period not to exceed 90 days upon consent of the Director and the applicant.
(B) Compliance with Permit Streamlining Act. If the permit requested is for a development project for construction or reconstruction subject to the Permit Streamlining Act (Government Code §§ 65920 et seq. ), the time limits provided in the Permit Streamlining Act shall apply to the Conditional Use Permit approval or disapproval.
(C) Time Limits for Appeals. Upon the filing of an appeal in compliance with Chapter 86.08 (Appeals), the Commission or the Board shall render its decision on the appeal within 60 days.
(b) Extensions of Time. Upon written request by the applicant, the County may extend the time for a planning permit or authorization to be exercised.
(1) Time for Filing of Request. The applicant shall file a written request for an extension of time with the Director at least 30 days before the expiration of the permit or authorization, together with the filing fee required in compliance with the County Fee Ordinance.
(2) Action on Extension Request. A permit or authorization may be extended as follows for no more than a total of 36 months for those applications listed in § 86.06.060(a)(1) and (2) above, except as noted below, beyond the expiration of the original approval.
(A) Evidence to Be Provided. The Director shall determine whether the applicant has made a good faith effort to exercise the permit or authorization. The burden of proof is on the applicant to establish, with substantial evidence, that circumstances beyond the control of the applicant (e.g., demonstrated problems with completing the acquisition of the parcel, poor weather during periods of planned construction, etc.) have prevented exercising the permit or authorization.
(B) Recommendations for Denial and Revocations. Recommendations for denial of a request for extension, and revocations of permits, shall be referred to the Zoning Administrator or the Planning Commission for public hearing and determination.
(C) Exceptional or Extraordinary Circumstances. Under exceptional or extraordinary circumstances, one or more extensions may be granted in addition to that provided in § 86.06.060(b)(2). In addition to the existence of
exceptional or extraordinary circumstances, the applicant must show that unreasonable delay to the project, if any, was not caused by the applicant.
(D) Findings. Requests for extensions shall only be granted if findings can be made that the project is consistent with the provisions of the General Plan and the San Bernardino County Code in effect at the time the extension request is considered.
(E) Phased Projects. This Subdivision shall not be applied to extend the time limits provided in § 86.06.060(a) (5)(B), above.
(3) Action on extension of a project subject to the Subdivision Map Act. The expiration date of a Tentative Map may only be extended in compliance with the Map Act § 66452.6.
(Ord. 4011, passed - -2007; Am. Ord. 4043, passed - -2008)
§ 86.06.070 Changes to an Approved Project. ¶
Development of a new land use authorized through a planning permit or authorization granted in compliance with this Development Code shall be established only as approved by the review authority, and in compliance with any conditions of approval, except where a change to the project is approved in compliance with Chapter 85.12 (Revisions to an Approved Action).
(Ord. 4011, passed - -2007)
§ 86.06.080 Resubmittals. ¶
(a) Resubmittal after Disapproval with Prejudice.
(1) The review authority may disapprove an application for a discretionary planning permit or amendment, on the grounds that two or more similar applications for the same parcel have been disapproved in the past two years (e.g., disapproval with prejudice), or that another cause exists for limiting the refiling of the application.
(2) For a period of 12 months following the date of the disapproval with prejudice of a discretionary planning permit or amendment, no application for the same or substantially similar planning permit or amendment shall be filed for the same site, or any portion of the site, except where the Director determines that substantial new evidence or proof of changed circumstances warrants further consideration.
(b) Resubmittal after Disapproval Without Prejudice. There shall be no limitation on subsequent applications for a site where a project was disapproved without prejudice.
(c) Director’s determination, appeal. The Director shall determine whether a new application is for a planning permit or amendment that is the same or substantially similar to a previously approved or disapproved permit or amendment, and shall either process or reject the application in compliance with this Section. The Director’s determination may be appealed to the Commission in compliance with Chapter 86.08 (Appeals). (Ord. 4011, passed - -2007)
§ 86.06.090 Covenants of Easements. ¶
(a) Applicability. When necessary to achieve the land use goals of the County, the County may require a property owner holding property in common ownership to execute and record a Covenant of Easement in favor of the County, in compliance with Government Code §§ 65870 et seq. A Covenant of Easement may be:
(1) Required to provide for emergency access, ingress and egress, landscaping, light and air access, open space, parking, or for solar access; and
(2) Imposed as a condition of approval by the review authority.
(b) Form of Covenant. The form of the Covenant shall be approved by the County Counsel, and the Covenant of Easement shall:
(1) Describe the real property subject to the easement and the real property to be benefitted by the easement;
(2) Identify the County approval or planning permit granted that relied on or required the Covenant; and
(3) Identify the purposes of the easement.
(c) Recordation. A Covenant of Easement shall be recorded in the County Recorder’s Office.
(d) Effect of covenant.
(1) From and after the time of its recordation, a Covenant of Easement shall:
(A) Act as an easement in compliance with Civil Code §§ 801 et seq. , except that it shall not merge into any
other interest in the real property. Civil Code § 1104 shall be applicable to the conveyance of the affected real property; and
(B) Impart notice to all persons to the extent afforded by the recording laws of the State.
(2) Upon recordation, the burdens of the Covenant shall be binding on, and the Covenant shall benefit all successors-in-interest to the real property.
(e) Enforceability. A Covenant of Easement shall be enforceable by the successors-in-interest to the real property benefitted by the Covenant and the County. Nothing in this Section creates standing in any person, other than the County, and any owner of the real property burdened or benefitted by the Covenant, to enforce or to challenge the Covenant or any requested amendment or release.
(f) Release of Covenant. A Covenant of Easement may be released by the Director, or by another appropriate
review authority in the event of an appeal, at the request of any person, including the County, or an affected property owner.
(1) Process for Release. The release of a Covenant of Easement shall require that the review authority first:
(A) Conduct a noticed public hearing in compliance with Chapter 86.07 (Public Hearings); and
(B) Find that the Covenant on the site is no longer necessary to achieve the land use goals of the County.
(2) Recordation. A notice of the release of the Covenant of Easement shall be recorded by the Director in the County Recorder’s Office.
(3) Fees. The applicant for a release of a Covenant of Easement shall pay the fee for the processing of the release in compliance with the Planning Fee Schedule.
(Ord. 4011, passed - -2007)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Bernardino County Zoning Code
- Chapter 81.01 — PURPOSE AND EFFECT OF DEVELOPMENT CODE
- Chapter 81.02 — INTERPRETATION OF REGULATIONS
- Chapter 82.01 — LAND USE PLAN, LAND USE ZONING DISTRICTS, AND …
- Chapter 82.02 — ALLOWED LAND USES AND DEVELOPMENT
- Chapter 82.03 — AGRICULTURAL AND RESOURCE MANAGEMENT LAND USE …
- Chapter 82.04 — RESIDENTIAL LAND USE ZONING DISTRICTS
- Chapter 82.05 — COMMERCIAL LAND USE ZONING DISTRICTS
- Chapter 82.06 — INDUSTRIAL AND SPECIAL PURPOSE LAND USE ZONING…
- Chapter 82.07 — ADDITIONAL AGRICULTURE (AA) OVERLAY
- Chapter 82.08 — AGRICULTURAL PRESERVE (AP) OVERLAY
- Chapter 82.09 — AIRPORT SAFETY (AR) OVERLAY
- Chapter 82.10 — ALTERNATE HOUSING (AH) OVERLAY
- Chapter 82.11 — BIOTIC RESOURCES (BR) OVERLAY
- Chapter 82.12 — CULTURAL RESOURCES PRESERVATION (CP) OVERLAY
- Chapter 82.13 — FIRE SAFETY (FS) OVERLAY
- Chapter 82.14 — FLOODPLAIN SAFETY (FP) OVERLAY
- Chapter 82.15 — GEOLOGIC HAZARD (GH) OVERLAY
- Chapter 82.16 — HAZARDOUS WASTE (HW) OVERLAY
- Chapter 82.17 — MINERAL RESOURCES (MR) OVERLAY
- Chapter 82.18 — NOISE HAZARD (NH) OVERLAY
- Chapter 82.19 — OPEN SPACE (OS) OVERLAY
- Chapter 82.20 — PALEONTOLOGIC RESOURCES (PR) OVERLAY
- Chapter 82.21 — SIGN CONTROL (SC) OVERLAY
- Chapter 82.22 — SPHERE STANDARDS (SS) OVERLAY
- Chapter 82.23 — COMMUNITY PLANS, SPECIFIC PLANS AND AREA PLANS
- Chapter 82.36 — OAK HILLS COMMUNITY PLAN
- Chapter 83.01 — GENERAL PERFORMANCE STANDARDS
- Chapter 83.02 — GENERAL DEVELOPMENT AND USE STANDARDS
- Chapter 83.03 — AFFORDABLE HOUSING INCENTIVES - DENSITY BONUS
- Chapter 83.04 — CONDITIONAL GRADING COMPLIANCE
- Chapter 83.05 — DEDICATIONS AND INSTALLATIONS OF STREET AND TR…
- Chapter 83.06 — FENCES, HEDGES, AND WALLS
- Chapter 83.07 — LIGHT TRESPASS
- Chapter 83.08 — HILLSIDE GRADING STANDARDS
- Chapter 83.09 — INFRASTRUCTURE IMPROVEMENT STANDARDS
- Chapter 83.10 — LANDSCAPING STANDARDS
- Chapter 83.11 — PARKING AND LOADING STANDARDS
- Chapter 83.12 — ROAD SYSTEM DESIGN STANDARDS
- Chapter 83.13 — SIGN REGULATIONS
- Chapter 83.14 — TRANSPORTATION CONTROL MEASURES
- Chapter 83.15 — CONDITIONAL COMPLIANCE FOR WATER QUALITY MANAG…
- Chapter 84.01 — ACCESSORY STRUCTURES AND USES
- Chapter 84.02 — ADULT BUSINESSES
- Chapter 84.03 — AGRITOURISM ENTERPRISES
- Chapter 84.04 — ANIMAL KEEPING
- Chapter 84.05 — BED AND BREAKFAST USES
- Chapter 84.06 — CEMETERIES
- Chapter 84.07 — COMMERCIAL AND INDUSTRIAL TRANSITIONAL USES
- Chapter 84.09 — FIREWOOD STORAGE
- Chapter 84.10 — GARAGE SALES
- Chapter 84.11 — HAZARDOUS WASTE FACILITIES
- Chapter 84.12 — HOME OCCUPATIONS
- Chapter 84.13 — MASSAGE SERVICES
- Chapter 84.14 — MOBILE HOME PARKS
- Chapter 84.16 — MULTI-FAMILY RESIDENTIAL DEVELOPMENT STANDARDS
- Chapter 84.17 — NONCONFORMING USES AND STRUCTURES
- Chapter 84.18 — PLANNED DEVELOPMENT STANDARDS
- Chapter 84.19 — RECYCLING FACILITIES
- Chapter 84.20 — SERVICE STATIONS
- Chapter 84.21 — SINGLE-FAMILY RESIDENTIAL DWELLINGS
- Chapter 84.22 — SMALL LOT RESIDENTIAL DEVELOPMENT
- Chapter 84.23 — LICENSED RESIDENTIAL CARE FACILITIES
- Chapter 84.24 — SOLID WASTE/RECYCLABLE MATERIALS STORAGE
- Chapter 84.25 — TEMPORARY STRUCTURES AND USES
- Chapter 84.26 — WIND ENERGY SYSTEMS - ACCESSORY
- Chapter 84.27 — WIRELESS TELECOMMUNICATION FACILITIES
- Chapter 84.28 — SHORT-TERM RESIDENTIAL RENTALS
- Chapter 84.29 — RENEWABLE ENERGY GENERATION FACILITIES
- Chapter 84.30 — GREENHOUSE GAS EMISSIONS REDUCTION PLAN IMPLEM…
- Chapter 84.32 — SMALL UNLICENSED RESIDENTIAL CARE FACILITIES
- Chapter 84.33 — EMERGENCY SHELTERS
- Chapter 84.34 — COMMERCIAL CANNABIS ACTIVITY
- Chapter 84.35 — INDUSTRIAL HEMP
- Chapter 84.36 — ACCESSORY DWELLING UNITS
- Chapter 85.01 — PERMIT APPLICATION FILING AND PROCESSING
- Chapter 85.02 — BASIC REVIEW PROCEDURES
- Chapter 85.03 — APPLICATION PROCEDURES
- Chapter 85.04 — ABC LICENSING
- Chapter 85.05 — CERTIFICATE OF LAND USE COMPLIANCE
- Chapter 85.06 — CONDITIONAL USE PERMIT/MINOR USE PERMIT
- Chapter 85.07 — FLOOD HAZARD DEVELOPMENT REVIEWS
- Chapter 85.08 — SITE PLAN PERMITS
- Chapter 85.09 — TENANT REVIEW
- Chapter 85.10 — PLANNED DEVELOPMENT PERMITS
- Chapter 85.11 — PRE-CONSTRUCTION FLOOD HAZARD MITIGATION AND E…
- Chapter 85.12 — REVISIONS TO AN APPROVED ACTION
- Chapter 85.13 — SIGN LOCATION PLANS
- Chapter 85.14 — SPECIAL USE PERMITS
- Chapter 85.15 — TEMPORARY USE PERMITS
- Chapter 85.16 — TEMPORARY SPECIAL EVENT PERMITS
- Chapter 85.17 — VARIANCES
- Chapter 85.18 — ACCESSORY WIND ENERGY SYSTEM PERMIT
- Chapter 85.19 — FOOD TRUCK EVENT PERMITS
- Chapter 85.20 — UNLICENSED RESIDENTIAL CARE FACILITIES PERMIT
- Chapter 85.21 — ADULT BUSINESS REGULATORY PERMIT
- Chapter 86.01 — PLANNING AGENCY
- Chapter 86.02 — DEVELOPMENT REVIEW COMMITTEE
- Chapter 86.03 — ENVIRONMENTAL REVIEW COMMITTEE
- Chapter 86.04 — FLOODPLAIN ADMINISTRATOR
- Chapter 86.05 — DECISIONS BY THE REVIEW AUTHORITY
- Chapter 86.06 — TIME LIMITATIONS
- Chapter 86.07 — PUBLIC HEARINGS
- Chapter 86.08 — APPEALS
- Chapter 86.09 — ENFORCEMENT
- Chapter 86.10 — AGRICULTURAL PRESERVES/LAND CONSERVATION CONTR…
- Chapter 86.11 — AIRPORT COMPREHENSIVE LAND USE PLANS
- Chapter 86.12 — AMENDMENTS
- Chapter 86.13 — DEVELOPMENT AGREEMENT ADOPTION AND AMENDMENT
- Chapter 86.14 — SPECIFIC PLAN ADOPTION AND AMENDMENT
- Chapter 86.15 — POST-DISASTER REBUILDING
- Chapter 87.01 — SUBDIVISION ORDINANCE APPLICABILITY AND ADMINI…
- Chapter 87.02 — TENTATIVE MAP FILING AND PROCESSING
- Chapter 87.03 — PARCEL MAPS AND FINAL MAPS
- Chapter 87.04 — ADDITIONAL SUBDIVISION PROCEDURES
- Chapter 87.05 — DEDICATIONS AND EXACTIONS
- Chapter 87.06 — SUBDIVISION DESIGN AND IMPROVEMENT REQUIREMENTS
- Chapter 87.07 — IMPROVEMENT PLANS, INSTALLATION, AND SECURITY
- Chapter 87.08 — SOIL REPORTS
- Chapter 88.01 — PLANT PROTECTION AND MANAGEMENT
- Chapter 88.02 — SOIL AND WATER CONSERVATION
- Chapter 88.03 — SURFACE MINING AND LAND RECLAMATION
- Chapter 89.01 — DRAINAGE FACILITIES FINANCING
- Chapter 89.02 — RECREATIONAL FACILITIES FINANCING
- Chapter 89.03 — TRANSPORTATION FACILITIES FINANCING