Document Package for Applicant's/Tenant's Consent to the Release Of Information
Example – Timely Tenant Response, But Delayed Verification Processing
HUD Handbook 4350.3 REV-1 — Occupancy Requirements of Subsidized Multifamily Housing Programs · 2026 edition · updated 2026-10-05 · United States
Recertification anniversary date is 9/1.
Owner sends out all notices in compliance with the requirements on 5/1, 6/1 and 7/1.
Tenant responds on 7/8.
Owner completes processing on 8/3.
Assistance payment changes on 9/1.
Rent increase is effective on 10/1.
D. Late Response/Processing of Recertifications
Delays in processing due to owner or third-party action.
a. This situation can occur as follows:
(1) The owner fails to provide timely recertification reminder notices per HUD requirements; or
(2) The owner has adequate time, but fails to complete verification and recertification processing procedures 30 days before the recertification anniversary date, and fails to provide the required 30-day notice for a rent increase to take effect on the recertification anniversary date.
b. Changes in the assistance payment take effect on the recertification anniversary date.
c.
Changes in the TTP and tenant rent are effective as follows:
(1) On the recertification anniversary date, if the tenant rent decreases as a result of the recertification; or
(2) On the first of the month following a 30-day notice period, if the tenant rent increases as a result of the recertification.
HUD Multifamily Occupancy Handbook Chapter 7: Recertification, Unit Transfers, and Gross Rent Changes
6/07
7-16
Section 1: Annual Recertification
4350.3 REV-1
Get a plain-English answer with a citation back to this text.
Ask AI about this code