3-8. PROCESSING INSTRUCTIONS
HUD Section 8 Renewal Policy Guidebook · 2026 edition · updated 2026-09-23 · United States
See Section 2-17 as modified below.
- A. Initially Eligible. The AE/CA must use the owner’s RCS to determine if the project is eligible for renewal under either Option One-A or One-B. The AE/CA, along with a
Chapter Three – Published March 2023
4
qualified appraiser, will also review the RCS based on the instructions found in Sections 9-17 through 9-20 of this Guide and determine whether the comparable market rent conclusions are reasonable. For transactions that include a RCS that has “as is” and “after rehab” market rent determinations as part of a Chapter 15 transaction, the AE/CA must use the “as is” market rents to determine initial eligibility.
B. Not Eligible.
If the project is not eligible for Option One-A, but meets the eligibility criteria for Option One-B, the AE/CA will notify the owner and request the owner to modify its renewal request.
If a project is not eligible for Option One-A or One-B,
a. In the case of a request for the early termination of an existing contract, the owner may be permitted to withdraw its renewal request entirely, in which case the existing contract would remain in place.
b. In all other cases the owner must switch to any other renewal option the project is eligible for including Option Six, Opt-Out. If an owner selects an option, other than Option One, then the owner’s RCS, subject to review described in Chapter 9 of this Guide, shall be used to determine the market rents for the project.
In the case where an existing contract has expired, the AE/CA may provide shortterm Renewal Contract at current rents to the owner while the owner determines the other renewal options for which the project may be eligible.
C. Comparability Studies. Along with a request to Mark-Up-To-Market, the owner must submit a RCS prepared following the guidelines detailed in Chapter Nine of this Guide.