12.13 Surveys

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Surveys must be by a licensed surveyor and show the exact location of on-site improvements, including utility lines and easements. Please see the FHA Multifamily Program Closing Guide for additional requirements related to survey matters.

B. The contractor must give the owner and HUD surveys, as follows:

  1. At any time, the owner or HUD requires; and

  2. When construction is complete (“as-built” survey).

MAP Guide, March 2021 Go to beginning of Chapter 12

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 12 Page 12-31

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 12 Construction Period 12.14 Permission to Occupy

Go to Table of Contents

C. The inspector, when uncertain of the location of construction or stored materials in relation to property lines or easements, may ask the Architect to require a survey with the next contractor's requisition.

D. If encroachments are found, the inspector must notify the HUD CA by memorandum explaining the conditions. (Encroachments may jeopardize the entire property as security for an insured mortgage.)

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.