19.5.5.6 Liquidated Damages
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. Article 3.E of the Construction Contract calls for the insertion of a liquidated damages amount, as determined by the RC Director. The following calculations are set forth for informational purposes:
Liquidated damages shall equal 1 cent for each ¼ per cent of construction interest rate for each $1000 of mortgage amount divided by the number of units. Written arithmetically and expressed in dollars (not
MAP Guide, March 2021 Go to beginning of Chapter 19
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Chapter 19 Page 19-64
To return to this page after clicking a link, press ALT + Back Arrow
Chapter 19 Closing Guide 19.5 Additional Requirements for Insurance of Advances
Go to Table of Contents
cents), the formula should read: ($.01) (construction rate/.0025) (mortgage amount/1000)/(number of units) = Liquidated Damages $/Unit/Day. This may be simplified and restated as: $4 x construction rate x mortgage amount/1000/number of units = Liquidated Damages $/Unit/Day.