19.5.5.6 Liquidated Damages

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Article 3.E of the Construction Contract calls for the insertion of a liquidated damages amount, as determined by the RC Director. The following calculations are set forth for informational purposes:

Liquidated damages shall equal 1 cent for each ¼ per cent of construction interest rate for each $1000 of mortgage amount divided by the number of units. Written arithmetically and expressed in dollars (not

MAP Guide, March 2021 Go to beginning of Chapter 19

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 19 Page 19-64

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 19 Closing Guide 19.5 Additional Requirements for Insurance of Advances

Go to Table of Contents

cents), the formula should read: ($.01) (construction rate/.0025) (mortgage amount/1000)/(number of units) = Liquidated Damages $/Unit/Day. This may be simplified and restated as: $4 x construction rate x mortgage amount/1000/number of units = Liquidated Damages $/Unit/Day.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.