3.2.8 Absorption Period

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. The absorption period used in estimating market demand for proposed newly constructed or substantially rehabilitated units should not exceed 18 months from delivery of the first units. The absorption period should be supported by the MAP Underwriter and fully explained in the Lender’s Narrative. Larger projects may phase in additional units under a separate application for mortgage insurance. An exception to the 18-month limitation on the absorption period may be considered by the Regional Center or Satellite Office Director for large high-rise buildings, which will be evaluated based on their own merit and will require a larger initial operating deposit.

MAP Guide, March 2021 Go to beginning of Chapter 3

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 3 Page 3-12

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 3 Programs 3.2 New Construction/Substantial Rehabilitation Program Requirements

Go to Table of Contents

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.