7.6.8.2 Cost/ Summation Approach

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. The cost or summation approach must consider all applicable forms of depreciation, functional, and external obsolescence. The cost/summation approach shall not automatically set the upper limit of value for these programs. The appraiser should provide a final reconciliation of the three approaches to value, and consider the basic principle of substitution in that no prudent purchaser would pay more for a project than the cost to acquire a similar site and construct improvements of equal desirability and utility. This approach may be eliminated at the discretion of the appraiser for subjects that are ten or more years old.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.