5.8.1 Plans and Specifications Revisions

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Except for projects submitted as streamlined applications, drawings and specifications may be amended by addendum when the change(s) will have no effect on cost or value (final drawings and specifications are finalized after Firm Commitment in streamline processing). The Lender’s Construction Analyst must review the addenda for acceptability as follows:

  1. Addenda must clearly state or show the change with specific reference to the location of the item on the drawings or in the specifications.

  2. Amendments shall be clearly noted and dated.

  3. Addenda are not to be used to correct errors noted during Firm Commitment processing.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.