5.3.3.2 When General Contractors are Required

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. The Borrower must hire a General Contractor to conduct all the work defined by the Project Architect and provide coordination as a single point of control for costs, scheduling, and conformance of the work to plans and specifications when one or more of the following conditions are true:

  1. The Aggregate Cost of repairs and alterations exceed $15,000 per unit, excluding General Contractor fees;

  2. The proposed work includes Level 3 Alterations; or

  3. More than three licensed trade contractors are to be employed for the work.

  • B. HUD may waive the requirement to hire a General Contractor when:
  1. The Aggregate Cost of all repairs and alterations exceeds $15,000 per unit but work is limited primarily to Repairs and Level 1 Alterations; or,

  2. The owner has substantial experience and proven ability planning and staging construction tasks, coordinating trades, and supplying general requirements.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.