13.11 Deficiencies in Cost Certification Submission

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. When the cost certification package is received for processing, the Cost and Mortgage Credit reviewers will:

  1. Determine deficiencies associated with the Borrower’s and contractor’s cost certifications.

  2. Advise the Regional Center Director and estimate the time needed to resolve the problem(s).

  3. Attempt to resolve all problems by telephone before making a formal written request. This usually allows processing to continue while waiting for a formal reply.

  4. Send a letter within 5 workdays to the Borrower with copies to the General Contractor (if applicable), their accountants, and the Lender stating the deficiencies and requesting information.

  • B. Upon receipt of all necessary information, combined processing should not exceed 15 workdays.

C. If the Borrower or contractor indicates clarification will be forwarded within 5 workdays, the conclusions of cost certification can await the additional information.

D. Otherwise, issue form HUD-92580.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.