19.4.11.8 Determinative Criteria for SLP Pre-Approval

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. The RC Director will approve the SLP as a temporary replacement GP/MM unless the RC Director, with the advice of the HUD Closing Attorney, reasonably determines that the SLP would not be an appropriate temporary replacement general GP/MM, or that such pre-approval is otherwise not in HUD’s interest. In

MAP Guide, March 2021 Go to beginning of Chapter 19

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 19 Page 19-54

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 19 Closing Guide 19.4 Document and Diligence Requirements

Go to Table of Contents

making such determination, the RC Director and the HUD Closing Attorney may consider the following factors:

  1. The number of projects the SLP and/or affiliated entities have under asset management;

  2. The number of times SLP and/or affiliated entities have replaced general partners/managing members and the results of such replacement. Specific examples should be provided and considered;

  3. The SLP’s process for monitoring projects and determining whether replacement of the general partner/managing member is appropriate; and

  4. How the asset management unit of the SLP and/or affiliated entities is staffed in relation to the number of projects it oversees.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.