A. When the Firm Commitment requires Borrower to fund construction of elements outside the Project’s property boundaries, HUD may require submittal of one or more of the following items, each at the discretion of the RC Director and in such form and substance as may be acceptable to the RC Director:
Plans and specifications for the off-site improvements;
Contracts or other agreements governing the construction of the off-site improvements;
Off-Site Bond (form HUD-92479M);
MAP Guide, March 2021 Go to beginning of Chapter 19
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Chapter 19 Page 19-66
To return to this page after clicking a link, press ALT + Back Arrow
Chapter 19 Closing Guide 19.5 Additional Requirements for Insurance of Advances
Go to Table of Contents
Escrow Agreement for Off-Site Facilities (form HUD-91071M);
A letter of credit;
Evidence of the locality’s plans for off-site improvements (if the municipality or other governmental locality will be responsible for completion of those improvements); and
Other evidence as deemed appropriate by the RC Director.