12.17.1.1 Completion of Repairs and Alterations

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. All critical repairs completed before initial closing. A site visit(s) and report(s) by a HUD representative are required to confirm satisfactory completion of critical repairs before closing. The only exception is critical accessibility repairs that HUD approved for deferred completion based on the complexity of the repair (see Chapter 5, Section 5.10.8.E). No other critical repairs may be deferred.

B. Non-critical repairs may be considered for deferred completion after closing at the request of the mortgagor. HUD will require the following schedules prior to approving the request:

  1. Schedule of Values (see Section 12.17.3 below) for payment of completed repairs;

  2. A progress schedule ensuring that repairs begin immediately upon closing and, with limited possible exceptions, are completed within 12 months of loan closing;

MAP Guide, March 2021 Go to beginning of Chapter 12

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 12 Page 12-41

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 12 Construction Period 12.17 Completion of Repairs and Alterations Pursuant to Section 223(a)(7) and 223(f)

Go to Table of Contents

  1. Schedule of Delayed or Interrupted Occupancy or Income, which must list:

    • All facilities or units for which occupancy or income will be delayed or interrupted by repairs deferred until after closing;
  • Estimated period of delayed or interrupted occupancy or income;

  • Projected completion date; and

    • An additional deposit must be made to an operating deficit account for delayed repairs that interrupt occupancy or income for any period. The amount of the additional deposit will be determined by HUD.
  1. Temporary Resident Relocation Schedule, when required.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.