12.14.1 Physical Completion
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. The work, or portion thereof for which Permission to Occupy is approved, must be sufficiently complete in accordance with the contract documents so the mortgagor can occupy or utilize the identified portion of the work for its intended use.
Support facilities (utilities, disability access, vehicular access and parking, fire life-safety equipment, etc.) must be in place.
The acceptability of each unit and facility for which Permission to Occupy is requested must be confirmed:
- Property must be inspected and form HUD-92485 signed by the Borrower, supervisory Architect, contractor, and HUD Representative.
Minor items that do not preclude occupancy are permitted but must be listed as an attachment to form HUD-92485.
The contractor is fully responsible for any incomplete or improperly performed contract work whether or not listed.