12.8.4 Deductive Change Orders

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Where the HUD estimated decrease in contract price for any aggregation of change orders remains less than 2-1/2% of the contract price, the Lender must reduce the Contractor’s “Final” Requisition, form HUD92448, by the appropriate amount.

  • B. Equals or exceeds 2-1/2% of the contract price and for all subsequent deductive change orders regardless of the amount, the Lender must:
  1. Reflect the decrease in the Contractor’s Requisition, form HUD-92448, item 8.

  2. Reduce the original mortgage amount at cost certification, where required.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.