12.8.4 Deductive Change Orders
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. Where the HUD estimated decrease in contract price for any aggregation of change orders remains less than 2-1/2% of the contract price, the Lender must reduce the Contractor’s “Final” Requisition, form HUD92448, by the appropriate amount.
- B. Equals or exceeds 2-1/2% of the contract price and for all subsequent deductive change orders regardless of the amount, the Lender must:
Reflect the decrease in the Contractor’s Requisition, form HUD-92448, item 8.
Reduce the original mortgage amount at cost certification, where required.