12.3.4.5 Shop Drawings and Other Data

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. During the construction period, the inspector must check whether shop drawings are being submitted by the contractor for approval by the Architect as required by the AIA General Conditions of the Contract.

MAP Guide, March 2021 Go to beginning of Chapter 12

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 12 Page 12-7

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 12 Construction Period 12.3 HUD Construction Inspection and Monitoring

Go to Table of Contents

Upon request by the Architect or the inspector, the contractor will keep copies of tests, certifications and any other data required by the contract documents onsite for review.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.