12.17.4 Final Report

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Final HUD Trip Report must be made upon completion of all work prepared by the HUD Inspector. The final report must show that:

  1. All work is acceptably completed in accordance with the firm commitment and/or closing escrow, as applicable, and approved changes;

  2. Offsite work is completed or that the municipality has given written assurance for its completion;

  3. Utilities are connected;

MAP Guide, March 2021 Go to beginning of Chapter 12

Bookmarked Version

Chapter 12 Page 12-45

Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 12 Construction Period 12.17 Completion of Repairs and Alterations Pursuant to Section 223(a)(7) and 223(f)

Go to Table of Contents

  1. Permanent ingress and egress facilities are provided; and

  2. Applicable municipal inspections, approvals, etc., have been issued.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.