12.17.4 Final Report
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. Final HUD Trip Report must be made upon completion of all work prepared by the HUD Inspector. The final report must show that:
All work is acceptably completed in accordance with the firm commitment and/or closing escrow, as applicable, and approved changes;
Offsite work is completed or that the municipality has given written assurance for its completion;
Utilities are connected;
MAP Guide, March 2021 Go to beginning of Chapter 12
Bookmarked Version
Chapter 12 Page 12-45
Go to Acronym and Abbreviation List, Glossary, Index
To return to this page after clicking a link, press ALT + Back Arrow
Chapter 12 Construction Period 12.17 Completion of Repairs and Alterations Pursuant to Section 223(a)(7) and 223(f)
Go to Table of Contents
Permanent ingress and egress facilities are provided; and
Applicable municipal inspections, approvals, etc., have been issued.