9.6.3.5 Requirements for New Construction

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

  • A. All new construction projects must follow radon resistant construction requirements.
  1. Multifamily structures reference ANSI-AARST CC-1000-2018, Soil Gas Control Systems in New Construction of Buildings.

  2. Single Family structures reference ANSI-AARST CCAH-2020, Reducing Radon in New Construction of 1 & 2 Family Dwellings and Townhouses.

B. Post-construction testing is required prior to final completion inspection. If post-construction testing results are above the threshold, the project must be brought into compliance by activating the mitigation system or through retrofit mitigation.

C. All testing and mitigation required as a result of this testing must be performed by, or under the direct supervision of a Radon Professional, in accordance with the protocols referenced in this section.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.