19.5.10.5 Escrow for Completion
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. With respect to all incomplete items, the amount held in escrow for completion must be at least one and one-half (1 ½) times the estimated cost of completion. The amount of any escrow must be sufficient to assure an incentive to complete the work, taking into consideration a possible rise in cost. The escrow will be held by Lender in accordance with the terms of Escrow Agreement for Incomplete Construction
MAP Guide, March 2021 Go to beginning of Chapter 19
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Chapter 19 Page 19-73
To return to this page after clicking a link, press ALT + Back Arrow
Chapter 19 Closing Guide 19.6 Requirements for Acquisition/Refinance and Other FHA Insurance Programs
Go to Table of Contents
(form HUD-92456M) (see Section 19.4.12.5) and the RC Director will ascertain that the items to be completed are properly identified by the attachment to the Escrow Agreement for Incomplete Construction.