13.4 Entities That Must Cost Certify
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. The Borrower must certify under all programs, except where HUD has determined at the time of issuance of the Firm Commitment that the insured mortgage under:
Section 221(d)/220/231 new construction/substantial rehabilitation is 80% or less of replacement cost and the project is will benefit from LIHTC, Historic Tax Credits or New Market Tax Credits; or
Section 207/223(f) refinance is 80% or less of value.
- B. When the Borrower is required to cost certify, the Contractor must also cost certify when:
The Contractor has an identity of interest with the mortgagor, whether such identity of interest existed or developed before or after the initial closing (for insured advances projects) or issuance of the Firm Commitment (for insurance upon completion projects); and/or
The Contractor used form HUD-92442M, Construction Contract-Cost Plus, whether or not any identity of interest with the Borrower existed or developed.
MAP Guide, March 2021 Go to beginning of Chapter 13
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Chapter 13 Page 13-5
To return to this page after clicking a link, press ALT + Back Arrow
Chapter 13 Cost Certification 13.5 Cost Certification Sequence of Events
Go to Table of Contents
C. When the Borrower is required to cost certify the subcontractors at any tier, equipment lessors, material suppliers, and manufacturers of industrialized housing must cost certify where:
The total of all subcontracts, purchases, and leases are more than 0.5% of the mortgage, and
An identity of interest exists or comes into being between such subcontractor, equipment lessor, material supplier, or manufacturer of industrialized housing and either:
- The Borrower; or
The contractor, where the contractor must cost certify.