B. Approved time extensions:

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

  1. Calculate the additional general requirements cost due to the extension of time.

    • Divide the cost of general requirements from the contractor’s approved form HUD-2328 by the number of months estimated for construction from Section G of form HUD-92264 approved at Firm commitment. Sixty-five percent of this amount is the estimate per month of additional general requirements.
  • Use one quarter of the monthly estimate per week.

  • There is no cost effect for extensions of time for less than one week.

  1. Complete the cost entries on form HUD-92437 and forward the completed form to the HUD Underwriter.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.