19.4.11.4 LIHTC Equity Pay-In

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

A. Pursuant to Chapter 14, Section 14.13, the LIHTC investor must contribute at least 20% of the total tax credit equity to the project at the time of Initial Endorsement (with the remaining 80% to be subsequently available). Note that Chapter 14, Section 14.13 allows 10% of the required total equity pay-in to be funded with an equity bridge loan at Initial Endorsement. The required minimum equity installment evidences the tax credit investor’s commitment to the Project. Tax credit equity installments must be made in accordance with either the disbursement agreement attached to the Building Loan Agreement (form HUD92441M) (for new construction and substantial rehabilitation), or the tax credit equity pay-in schedule attached to the Escrow Agreement for Deferred Repairs (form HUD-92476.1) (for loans closed pursuant to 223(f).

  1. Lender must submit satisfactory evidence of an agreement that obligates the tax credit investors to make timely and periodic payments to the Borrower of the tax credit equity (typically the limited partnership agreement), which Borrower will use for Project completion costs.

  2. See Section 19.4.9.6 and Chapter 14, Section 14.15 for additional guidance on equity bridge loans.

MAP Guide, March 2021 Go to beginning of Chapter 19

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Chapter 19 Page 19-52

To return to this page after clicking a link, press ALT + Back Arrow

Chapter 19 Closing Guide 19.4 Document and Diligence Requirements

Go to Table of Contents

  1. Note: Pursuant to Housing and Economic Development Recovery Act of 2008 (HERA), and 24 CFR 200.54, HUD cannot require 100% of the tax credit equity be escrowed at closing.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.