A.13.2 Agreement Authorizing Deferment of Principal Payments for Level Annuity Monthly Payment

Definition

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

503.1]. Examples include removing and replacing an existing flooring or wall finish, etc.

Level 2 Alterations Level 2 Alterations: “…include the reconfiguration of space, the addition or elimination of any [exterior] door or window, the reconfiguration or extension of any system, or the installation of any additional equipment.” [IEBC Section 504.1]

Examples include:

  1. adding or demolishing interior walls (partition or loadbearing) to reconfigure dwelling unit layout;

  2. adding another bathroom inside a unit;

  3. relocating the kitchen within a unit;

  4. adding a new air conditioning system that was not previously present to the existing buildings and/or units;

  5. adding an elevator to the building, etc.

Level 3 Alterations

Level 3 Alterations: “…apply where the work area consisting of all reconfigured spaces exceeds 50% of the building area.” [IEBC Section 505.1]

level annuity monthly A monthly payment plan through which all HUD insured mortgages must payment plan (LAMP) fully amortize with equal monthly payments of principal and interest. Fully amortize means that the entire principal amount of the loan is repaid.

Liquidated damages Liquidated damages…[are] funds to pay for overruns in interest, taxes, MIP and insurance (soft costs) that are due to construction delays that are the General Contractor's fault. The funds are provided by the General Contractor, most often by means of a reduction in amounts otherwise due to the General Contractor consistent with the General Contract.

  • Loan Consultant The term applies to an individual or firm actively engaged in the mortgage origination business and acting as an intermediary with or on behalf of the MAP Lender but who is not a MAP-approved Lender themselves and is not an employee of a MAP Lender or of an affiliate of the Lender. Under MAP, the consultant’s sole role is to refer new business to a MAP Lender including information supplied by the proposed borrower/sponsor. Aside from referring a Borrower/Sponsor for a MAP loan, a consultant may not have any additional role in underwriting the transaction.

Loan-to-Value Ratio See "Criterion 3".

Low-Income Housing A tax incentive intended to increase the availability of low-income housing. Tax Credit program The program provides an income tax credit to owners of newly constructed (LIHTC) or substantially rehabilitated low-income rental housing projects.

Lump Sum A lump sum contract is a construction agreement in which the contractor Construction Contract agrees to complete the project for a fixed price. This is one of only two options for construction contracts in HUD insured mortgage transactions. See also "Cost-Plus Contract".

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Term Definition
Management Entity HUD form HUD-9832 Management Entity Profile for the Agent provides
Profile detailed information regarding the organization, operation, and experience
of the proposed management agent.
MAP Lender Includes the Lender’s officers, directors, partners, principals, stockholders,
affiliates, affiliate’s officers, affiliate’s principals or any contract employees
working on a particular affiliate’s or principal’s MAP application and, unless
otherwise specified, includes the FHA-approved MAP Lender, its parent
company, subsidiaries, affiliates and any other related entities, and any
officers, directors, partners, members or employees of the MAP Lender, its
affiliates and other related parties.
Market Study A market study assures that there is enough sustainable demand for
additional units without adversely impacting the existing supply, so as to
maintain a balanced overall market. The focus of the market study is on the
overall demand within a defined market area, and of the proposed project’s
ability to capture and sustain a share of the total (incremental demand).
Market studies estimate the number of renter households with sufficient
incomes to afford the type of housing at the rents proposed at present, as
well as any expected changes in rental housing demand in the foreseeable
future (typically the next 3 to 5 years).
Master Lease Master leases are structured to permit a combination of investments by one
or more investors under one or more tax credit programs in a single
development project. Generally, the Master Lease structure involves the
following parties, which often have total or partial identities of interest and
common ownership:
1. FHA Borrower – the Single Asset Entity (the Lessor for the Master
Lease);
2. Master Tenant – the lessee; and
  1. Master Lease Sub-lessees for Residential units, and for Commercial space.
  • Medium risk Medium risk transactions include, for example, 223(f) projects where transactions significant repairs may be required, RAD or Tax Credit projects as well as Substantial Rehabilitation projects where there is minimal tenant displacement.

  • Merchant builder Merchant builders, also referred to as merchant developers, are firms whose business practice is to build properties, lease them to a point of sustaining occupancy, sometimes holding them for a short additional period of seasoning, and then selling them.

  • Mezzanine financing Mezzanine financing is a loan usually secured by a pledge of ownership interests, rather than by a lien on the real estate or an obligation of the Single Asset Mortgagor Entity.

Monthly Requisition For an insured mortgage with insured advances, a contractor’s monthly requisition (request for payment), which must be made on form HUD-92448.

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Term Definition
Mortgage insurance For each FHA-insured mortgage loan, FHA charges an initial mortgage
premium (MIP) insurance premium at closing plus a monthly mortgage insurance premium.
Mortgageable costs Mortgageable costs means the costs for acquisition of property, construction,
repairs, organizational costs, legal counsel, financing costs, due diligence
costs, recording costs and other costs typical of commercial real estate
transactions. But for insured mortgage practice the MAP Guide provides
specific guidance on the eligibility and measurement of costs and this
guidance appears throughout the MAP Guide consistent with subject matter
considered. The best characterization of mortgageable costs are found in
Chapter 8, Section 8.10through Section 8.15 summarizing how to determine
mortgage amounts under the various sections of the act and possible
circumstances. Additional detail on what is and is not an eligible cost may be
found in Chapter 13, Section 13.14 and Section 13.15 describing review of
the owner and contractor's certified costs.
Named insured Any person, firm, or organization, or any of its members specifically
designated by name as an insured(s) in an insurance policy, as distinguished
from others that, although unnamed, fall within the policy definition of an
"insured."
National Housing Act The National Housing Act, aka "the Act," is a law passed by Congress and
signed by the president in 1934 establishing the Federal Housing
Administration (FHA) and authorizing it to operate certain mortgage
insurance programs. Since 1934, Congress has repeatedly amended the Act
adding and deleting Sections, establishing new or modifying existing
authorizations and defining basic requirements. HUD mortgage insurance
programs are typically known by the section of the Act in which the
Congress authorized the particular insured mortgage activity, e.g., current
programs, Sections 220, 221(d)(4), 223(f), 223(a)(7), 231, 241(a).
Needs assessor A professional with education, professional credentials, and field experience
appropriate to conduct a capital needs assessment of a property considering
the age, size, type of building systems, construction methods, and location of
the property.
Net Demand An estimate of future demand for the specified forecast period, typically 36
months. The estimate of demand must be based on a calculation of
incremental demand (i.e. demand for additional new units).
Net Equity The term “Net Equity” is used in reference to Low Income Housing Tax
Credit transactions and is defined in Chapter 14, Section 14.14. It is Total
Equity less the initial 20% installment less “Delayed” Developer Fees for
amounts due after the completion of repairs or construction and
predetermined reserve amounts to be held by the investor for project uses
after the time of the final pay-in.
Net operating income NOI is the income remaining after subtracting all operating expenses from
(NOI) rents and other income collected for a property for a given period, but before
payment of debt service.

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version

Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Term Definition
Non-critical repair Critical and Non-Critical repairs are identified by the needs assessor who
prepares a capital needs assessment for an existing property. SeeAppendix
5, Section A.5.7.2.2for discussion of critical and non-critical repairs. Non-
critical repairs are repairs that are needed currently or within not more than
two years following endorsement or repairs intended by the owner to
upgrade or modernize a property. The completion of non-critical repairs
may be deferred until after endorsement but should not require more than
one year to complete.
Non-profit Principal The term "Nonprofit Principal" is understood to mean “the Single Asset
Entity (SAE) Borrower and its Board of Directors”. SeeChapter 8, Section
8.3.4.
Office of Lender The HUD Office that determines whether a lender is an FHA-approved
Activities and mortgagee pursuant to 24 CFR Part 202.
Compliance
Offsite (off-site) Offsite work is work adjacent to project boundaries including utilities, walks,
Construction curbs, gutters, streets, drainage structures, landscaping, etc., that extend
away from the project site. These improvements are not included in the
construction contract. See Chapter 5, Section 5.12.2.B.2.
Operation and An operation and maintenance plan (O&M) may be a written general plan for
Maintenance Plan (O physical operation and maintenance of a property with schedules for routine
& M) maintenance tasks, etc. But in HUD insured mortgage practice an O&M plan
means a plan for addressing ongoing hazards, physical risks, essential
equipment, and testing and record-keeping to assure that an identified
hazard is managed safely. HUD requires an O&M plan to address hazardous
materials or environmental conditions which may continue in place safely as
long as correct procedures are timely observed. The O&M plan describes the
procedures. SeeChapter 9, Section 9.6.21.
Opportunity Zone An economically distressed community where new investments, under
certain conditions, may be eligible for preferential tax treatment. Localities
qualify as Qualified Opportunity Zones if they have been nominated for that
designation by a state, the District of Columbia, or a U.S. territory and that
nomination has been certified by the Secretary of the U.S. Treasury via his
delegation of authority to the Internal Revenue Service (IRS).
Owner's The owner's representative must be a member of the Borrower entity,
Representative usually a general partner or managing member with authority to make
decisions to fulfill owner's responsibilities during construction. Non-profit
organizations may be represented by an executive officer or member of the
Board of Directors.
Partial Occupancy Refers to allowing some units to be occupied in a property before the
property as a whole obtains a Certificate of Occupancy.
Participants In the context of the MAP Guide, participants are those involved in the
preparation, processing, and submission of applications for FHA multifamily

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Term Definition
mortgage insurance, including HUD staff, Lenders, third party consultants,
Borrowers, and others.
Passive Principal “Passive Principals” are persons or entities who singly or with others have
limited or no decision-making power or control over the Borrower but who
have an ownership interest of 25% or more (10% for corporations) in the
Borrower.
Penetration Rate Penetration Rate is defined as the percentage of Qualified Renter Households
in the PMA that the property and similar existing and proposed competing
properties must capture to fill all units and achieve stabilized occupancy.
The Penetration Rate is calculated by dividing the total number of units in
the competitive inventory (including the subject property, current
competitive properties, and proposed relevant competitive properties) by
the total number of renter households that meet the applicable age and
income eligibility band requirements.
Performance and A performance bond is a surety bond that is issued by a bonding company or
Payment Bond bank to guarantee satisfactory completion of a project by a contractor. It
protects the owner in case the contractor fails to complete the contractual
obligations. Payment bonds are a guarantee that the contractor will pay all
laborers, material suppliers, and contractors per contractual obligations.
Performance Based The PBCA is an agency hired to assist HUD/OAMPO in the administration of
Contract Section 8 HAP contracts.
Administrator (PBCA)
Permission to Occupy Permission to rent or occupy specific living units, commercial, or other space
in a building. Units and spaces should not be occupied prior to approval by
HUD.
Phase I The Phase I Environmental Site Assessment (ESA) is required for most HUD
Environmental Site mortgage insurance applications for new construction and substantial
Assessment (ESA) rehabilitation. See Chapter 9, Section 9.1.3.C.5.A Phase I ESA is a broad fact
finding and analytical report as characterized in Chapter 9, Section 9.4.1and
Section 9.6.20, identifying environmental impacts of a proposed project,
hazards that may exist, environmental features or significant artifacts the
may require protection. The American Society for Testing and Materials
(ASTM) has published standards for preparation of Phase I ESAs.
Phase II A Phase II Environmental Site Assessment (ESA) is a follow-on study to a
Environmental Site Phase I ESA and is intended to address conditions observed or identified in a
Assessment (ESA) Phase I EIS. For detailed discussion see Chapter 9, Section 9.4.2. ASTM
publishes standards for Phase II ESAs.
Pre-Construction A pre-construction conference conducted by the HUD Inspector or HUD CA is
Conference required for every new construction and substantial rehabilitation project
and must precede the initial start of construction, including early start of
construction.

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Term Definition
Pre-Cost Certification A meeting that should be held before the project is 90% complete at which
Conference HUD staff will explain: substantial completion, administrative completion,
and cut-off dates; documentation required for cost certification;
responsibility of the borrower and accountant for computing the liquidated
damages/ actual damages and incentive portions, if applicable, of the
construction contract; necessity for a careful review and completeness of the
documentation; and any problems with prevailing wage certifications or
other labor issues.
Prevailing wage rates All contractors engaged at job sites covered by the Davis-Bacon (i.e. all
(David-Bacon Wage insured mortgage construction loans) must pay their laborers and
Determination) mechanics the locally prevailing wages and fringe benefits for corresponding
work on similar projects in the area. The Davis-Bacon Act directs the
Department of Labor to determine such locally prevailing wage rates which
determination is made for each project and is called a "wage decision." See
"Davis-Bacon Act."
Previous participation Individuals and entities in control of a project are subject to a previous
review participation review as set forth in 24 C.F.R. Part 200, as the same may be
amended from time to time, and must submit information
regarding previous participation in governmental housing transactions
either via the electronic Active Partner Participation System (APPS) or on
form HUD-2530, or any successor system or form, for approval for
participation in any mortgage insurance program.
Primary Market Area The Primary Market Area (PMA) is the geographic area in which units with
(PMA) similar characteristics (e.g., number of bedrooms and rents) are in equal
competition.
Prior Credit Approval Prior credit approval of a principal is a specialized review of a person or
entity who is a repeat customer of HUD insured mortgage programs and
whose aggregate unpaid insured loan balances exceed $500 million. This
scale of HUD activity is a risk exposure for HUD that requires analysis of
existing and proposed additional exposure before HUD will allow the person
or entity to pursue additional insured multifamily debt. See also
"Concentrated Risk" and Chapter 8, Section 8.6 and Appendix 8, Section
A.8.3.
Privacy Act The Privacy Act of 1974, as amended, 5 U.S.C. § 552a, establishes a code of
fair information practices that governs the collection, maintenance, use, and
dissemination of information about individuals that is maintained in systems
of records by federal agencies. A system of records is a group of records
under the control of an agency from which information is retrieved by the
name of the individual or by some identifier assigned to the individual.
Processing Refers to the processing of mortgage insurance applications by HUD.
Program Obligation All applicable statutes and any regulations issued by the HUD Secretary that
(Loan obligation) apply to the Project, including all amendments to such statutes and
regulations, as they become effective. Also, all current requirements in HUD

MAP Guide, March 2021 Go to beginning of Glossary

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

To return to this page after clicking a link, press ALT + Back Arrow

Glossary

Go to Table of Contents

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.