A.12.2 Contractor’s Monthly Requisition
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
A. Contractor’s monthly requisition must be made on form HUD-92448. The Contractor’s Prevailing Wage Certificate on the form’s reverse side must be signed. (The HUD Construction Manager should contact HUD Labor Standards and Enforcement staff if there are any outstanding questions regarding Davis-Bacon weekly payrolls and/or possible underpayment of Davis-Bacon prevailing wages.) The HUD Inspector reviews for acceptability. If acceptable, forward to MAP Lender’s mortgage credit analyst for further processing.
- B. Eligible Items for Inclusion on form HUD-92448 include:
- Acceptably completed onsite work, i.e. in full compliance with contract documents.
MAP Guide, March 2021 Go to beginning of Appendix 12
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Appendix 12 Page A12-8
To return to this page after clicking a link, press ALT + Back Arrow
Appendix 12 Construction Period A.12.2 Contractor’s Monthly Requisition
Go to Table of Contents
Materials acceptably stored onsite, itemized by quantity and cost, with supporting invoices.
Components acceptably stored offsite, where provisions are made at initial closing in accordance with Chapter 12, and requirements of Appendix 12, Section A.12.3 below are met.
- C. The Architect determines amounts due by job site observation of acceptable work. (The HUD Inspector makes the determination if there is no Architect.)