Appendix 2 Quality Control Plans and Identity of Interest

A.5.4.1 Required Exhibits for New Construction

HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States

  • A. Property site related exhibits must include the following
  1. Location map;

  2. Aerial photograph or satellite images for each site showing existing conditions and full site labeled by property name and site address;

  3. Soils investigation, geotechnical and foundation design report.;

  4. USGS Seismic Threshold Report;

  5. Municipal and utility company letters of confirming availability of service; and

  6. Documents evidencing site ingress and egress and other general criteria per MPS (Handbook 4910.1) Chapter 2.

  • B. Property legal exhibits must include the following:
  1. Zoning compliance and Building Department Review permit, including Fire Department approval;

  2. City/County Health Officer’s report/permit, where private water supply or sewage treatment systems are involved; and

  3. Drafts of proposed joint use, access, and maintenance agreements where common use easements are anticipated.

  • C. Construction Documents must include:
  1. Drawings and Specifications conforming to Appendix 5, Section A.5.5; and

  2. Offsite Construction descriptions conforming to Appendix 5, Section A.5.5.

  • D. Contracts and Certifications must include:
  1. AIA B108 with HUD Amendment to AIA Document B108 (form HUD-92408-M);

  2. Appendix 5, Section A.5.8.1 Architect’s Certification;

  3. Form HUD-92442M, Construction Contract; and

  4. AIA A201 with HUD Supplementary Conditions to the Contract for Construction (HUD 92554M).

MAP Guide, March 2021 Go to beginning of Appendix 5

Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index

Appendix 5 Page A5-21

To return to this page after clicking a link, press ALT + Back Arrow

Appendix 5 Architectural and Construction Analysis A.5.4 Construction/Architectural Documents for Firm Commitment

Go to Table of Contents

  • E. Architectural and cost analysis report, with cost related exhibits must include:
  1. Architectural Analysis Report;

  2. Cost Analysis Report;

  3. Form HUD-2328, Contractor’s and/or Mortgagor’s Cost Breakdown;

  4. Form HUD-92326, Project Cost Estimate; and

  5. Form HUD-92331-B, Cost Certification Review Worksheet.

  • F. The CNA e-Tool must include required data to produce the following:
  1. Completed physical inventory of the property to be constructed (i.e., assessment entry screens for Sites, Buildings, Unit Types, Units and Common Spaces, Parking, Components, Alternatives and Recommendations, and Financial Factors).;

Units Inspected and Narrative Sections are not required to be completed.

  • TCO (Total Cost to Operate) and Energy-related fields are required only for Green MIP and underwriting energy savings transactions.
  1. Estimate of Replacement Costs (form HUD-92329, Schedule of Insurable Values Report) related information; and

  2. Financial Factors, Future Needs, and Financial Schedule/Estimate Period Recap for Reserve for Replacement escrow deposit amounts.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.