Appendix 2 Quality Control Plans and Identity of Interest
M.10–Parking
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
Parking lot paving: 15,000 sf x 1.25 18,750 Parking lot curbing: 500 lin. ft. x 10.50 +5,250 Parking bumpers: 50 x 30.00 +1,500 Catch basins: 4 x 1500.00 +6,000 Storm drain: 350 lin. ft. x 27.00 +9,450 Striping: 50 x 4.00 +200 Summary Cost =$41,150 M.13–Special Exterior Land Improvements Patio paving: 400 sf x 4.00 1,600 Patio benches: 6 x 500.00 +3,000 Patio tables: 6 x 1000.00 +6,000 Ornamental shrubs: 12 x 100.00 +1,200 Playground paving: 900 sf x 2.00 +1,800 Safety surface: 900 sf x 3.00 +2,700 Swing sets: 2 x 500.00 +1,000 Slides: 2 x 1000.00 +2,000 Summary Cost =$19,300 M.14–Other Community room: 650 sf x $55.50 =$36,075
Total Summary Costs = M.10 + M.13 + M.14 = Total “B” Costs = $96,525
Enter summary costs and breakdown in Section M.
MAP Guide, March 2021 Go to beginning of Appendix 5
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Appendix 5 Page A5-68
To return to this page after clicking a link, press ALT + Back Arrow
Appendix 5 Architectural and Construction Analysis A.5.11 Costs Not Attributable for Existing Properties
Go to Table of Contents
- “A” Costs
Total Structures (form HUD-92264, line $1,665,000 G.41)
Total Land Improvements (line G.3 5c) +250,000 TOTAL “A” COSTS =$1,915,000
Cost Not Attributable (B over A):
- “B” costs @ $96,525 divided by “A” costs @ $1,915,000 = 0.0504 = 5.04 percent
- Enter the percentage in Section M of form HUD-92264.