Appendix 2 Quality Control Plans and Identity of Interest
A.5.9.1 Cost Review Report for Pre-Application
HUD Multifamily Accelerated Processing (MAP) Guide, HUD Handbook 4430.G (2020 ed., rev. Mar. 19, 2021) · 2026 edition · updated 2026-10-05 · United States
- A. Cost Review Report for Pre-Application:
HUD Office Name:
Pre-Application Submission Date: Project Name: Project Location (City, State): MAP Lender Name:
- B. Summary of HUD cost review:
Cost exhibits. If not acceptable, indicate reasons.
Mortgagor’s Architect’s sketch plans
Form HUD-92013
For Substantial Rehabilitation projects, include the following. If not acceptable, indicate reasons .
Mortgagor’s Architect’s Scope of Work Summary
Mortgagor’s summary cost estimate for substantial rehabilitation (based on Scope of Work Summary)
HUD Cost Estimate determination. If not acceptable, indicate reasons.
MAP Guide, March 2021 Go to beginning of Appendix 5
Bookmarked Version Go to Acronym and Abbreviation List, Glossary, Index
Appendix 5 Page A5-60
To return to this page after clicking a link, press ALT + Back Arrow
Appendix 5 Architectural and Construction Analysis A.5.9 HUD Cost Reviewer Reports Format
Go to Table of Contents
Structure type (from sketch plans):
Gross floor area (from sketch plans):
Estimated Total Structures cost (from cost data):
For Substantial Rehabilitation, indicate major trade item groups (if required), and subtotals:
Estimated Total Land Improvements cost (from cost data):
Estimated General Requirements (from cost data):
Estimated fee items (from cost data):
- General Overhead
- Builder’s Profit
- Architectural Fees
- Bond Premium
- Other Fees
Review of mortgagor’s form HUD-92013. If not acceptable, indicate reasons .
- Percentage difference between mortgagor’s Total Structures cost (Section G, Line 8) and HUD Cost Estimator’s Total Structures cost:
Percentage difference between mortgagor’s Total Land Improvements cost (Section G, Line 3) and HUD Cost Estimator’s Total Land Improvements cost:
Percentage difference between mortgagor’s General Requirements and fees (Section G, Lines 10 through 19) and HUD Cost Estimator’s General Requirements and fees:
C. I have reviewed the subject project and hereby make the following recommendation(s):